5. Installation and Operation

Installation and operation may only be conducted by authorized and qualified personnel.
5.1 Installing FPN5590B
Install the FPN5590B in the prescribed position, on aflat, clean surface, and fasten with four M4
screws. The maximum allowed penetration of the mounting screws is 6 mm (7/32 in.)
The recommended screw tightening torque is 1.27 N×m (13.0 kgf×cm).
5.2 Connecting FPN5590B to Backup Battery and Radio
Warning
M5 screws are used on the terminal strip. The recommended screw tightening torque is 2.50 N×m
(25.5 kgf×cm).
Battery and Radio Connections
5.3 Operating Instructions
1. Set the ON/OFF switch to OFF.
2. Connect the AC power cable to the prescribed outlet.
3. Set the ON/OFF switch to ON. Check that the green ON indicator turns on.

6. Cleaning

Remove dirt with soft, clean brush.
Clean external surfaces only with soft cloth moistened with water. Avoid extensive contact with water.
Risk of explosion if incompatible battery is used or battery is incorrectly