Lift sling
Figure 2-2: Recommended Lifting Method (Side View)
Figure 2-3: Corner Warning Label
Forklifts
When using a forklift to raise the lineup, proceed as follows:
1. Expand forklift tines to their maximum (widest) extension.
2. Carefully insert tines of forklift below one side of the enclosure
at the approximate center of the panel as shown in Figure 2-4.
3. Raise equipment and proceed to transport the enclosure.
4. Carefully lower the enclosure until it rests stable at its
final destination.
Figure 2-4: Placing Forklift Tines under Equipment Shipping Skid
Using Rollers
Figure 2-5: Method of Moving
After shipping skids are removed, roller may be used to roll
equipment parallel to front only.
SecoGear – Installation, Operation and Maintenance Manual 14 of 56
Front view
Lifting plates must
be removed where
sections are joined,
during installation
Side view
Roller