Verifying Hardware Installation; Checking Electrical Connections - Huawei PDU8000 Quick Installation Manual

Ups pdc
Hide thumbs Also See for PDU8000:
Table of Contents

Advertisement

3. Connect the maintenance bypass input
power cables.
5. Connect signal cables.
6
Check Before Power-On Commissioning

Verifying Hardware Installation

6.1
No.
Check Item
The cabinet is clean, without redundant screws, copper wires, or
1
other debris.
2
The paint on the cabinet exterior is intact.
3
The cabinet door and lock work properly.
4
All safety marks and warnings are correct, clear, and complete.
There is no adhesive tape, cable tie, paper scrap, or packing
5
material around the cabinet.

Checking Electrical Connections

6.2
No.
Check Item
1
All cables are connected correctly.
2
Ground cables are securely connected.
Power cables and ground cables are not coiled and extra parts
3
are cut off.
4
The phase sequence is correct.
5
All circuit breakers are OFF.
4. Connect the UPS load output power cables.
13
Check Result
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail
Check Result
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail
□Pass □Fail