Handling precautions

1. Panel mounting
①Be sure to connect the "E" terminal of the relay to D-
class grounding.
②The relay of unit-drawer type (RD type) can be drawn
out from the case.
2. Use and operation
①About the setting switches for using condition, factory
settings are set to a default of OFF. So it is necessary
to set the switches according to the conditions.
②Please refrain from changing the setting value during
operation, since unwanted operation may occur. However,
if the setting change is unavoidable, please press the
CPU reset button in order to lock the relay function.
Test
A relay test is carried out sufficiently before shipment,
but at the following cases, it is recommended the test
should be carried out again.
a. When the products are delivered and unpacked
b. At the time of starting operation of equipment
c. At the time of periodic inspection (Usually once a
year)
1. At the time of testing
①The input waveform should be a sine wave with little
distortion.
②During the test, set the position of the indicator
select switch to "V
0
MEASURE", or "PICKUP". Set the other setting switches
according to the test conditions of the operating
characteristic control point.
③ If user-defined control point is specified (e.g.
accuracy of relay characteristic is controlled at
service
conditions),
manufacturer-defined
before in-service operation and then check accuracy of
the relay. After that, execute the test at the user-
defined control point, and use this data as a later
reference.
④Perform the test in combination with ZCT (MZT type) and
ZVT (MPD-3 type). Otherwise, direct input to the relay
may cause burning out.
2. Withstand voltage test
a. Please disconnect the relay from ZCT and ZVT. If a
voltage higher than the rated value is applied, it
may burn out.
MEASURE", "I
MEASURE", "PHASE
0
execute
the
test
characteristic
control
③Don't leave rotary switches with halfway (indefinite)
state.
④The RUN LED lights up in the normal condition when the
rated auxiliary power supply is input. If it still turns
off when the auxiliary power supply voltage exceeds 85V,
please contact our local agent and branch office since
the relay may fail.
3. Connection of V
①Be sure to connect the V
MPD-3 type ZVT or the MDG relay supplying V
on the relay power supply.
b.
Apply 2000V AC (commercial frequency) between all
circuits and earth (E terminal) for one minute, and
make sure that there is no problem.
Y1
Z1
Y2
Z2
c. Apply 2000V AC (commercial frequency) between separate
circuits for one minute, and make sure that there is
no problem.
at
the
point
Note) Never apply a test voltage between these circuits.
Y1
Y2
Z1
Z2
15
input terminal
0
input terminal (Y1-Y2) to the
0
Voltage applied terminals
P1
M
a11
a12
P2
N
a21
a22
Voltage applied terminals
P2
P1
Y1
Y2
a11
Z1
Z2
M
N
P2
P1
P2
P1
P1
P2
,
Z1
Y1
M
Z2
Y2
M
N
when turning
0
E
a11
a12
a21 a22
a11
a12
a21 a22
a12
a21 a22
a11
a12
a21 a22
Y1
Y2
Z2
Z1
M
N
,
N
JEP0-IL9554

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Melpro mdg-a3v-rMelpro mdg-a3v-rd

Table of Contents