Locate area for pedestal location.
Install two conduits, one for power, and one for communication (if required). Allow approximately 5"
length for each conduit above the concrete level as shown in Figure 4. Cut as necessary to final
dimensions. Route power conduit and communication conduit through the center of the hole in the
mounting template, appropriately.
Install base mounting assembly plate securely over conduits with mounting template and four 1/2-13
nuts.
GE EV Charging Station User Manual
CONDUIT
MOUNTING TEMPLATE
CONCRETE
BASE MOUNTING
ASSEMBLY
WARNING: Make sure power to the EVSE is
disconnected before performing any task
User Manual & Installation Instructions
Figure 3