Download Print this page

ABB DB BREAKER Retrofitting Manual page 9

Advertisement

7
MAKING THE SYSTEM SAFE FOR REMOVAL
The following warnings and precautions must be respected
before removing the CiC adapter and circuit breaker from
the switchgear.
Place the switchgear housing and the circuit breaker
out of service.
Disconnect the power from the switchgear
(power circuit and auxiliary circuits) and verify it is
disconnected from all sources of energy.
Double check to ensure that the line has been placed
out of service.
NOTE: The trained personnel in charge of handling and lifting
must use appropriate safety equipment.
Remove the Emax 2 CiC Adapter
WARNING: THE CIRCUIT BREAKER COULD DROP
DURING THIS OPERATION. FASTEN IT TO A
LIFTING TRUCK BEFORE PROCEEDING.
Ÿ Remove the Emax 2 circuit breaker, refer to the
Emax 2 manual 1SDH001000R0002.
Ÿ Unscrew the racking lock pins on
each side of the CiC adapter until they are clear
of the racking pins as shown in (fig. 9).
Ÿ Use DB rack out tool to disengage CiC
adapter with stabs as shown in (fig. 10).
Ÿ Note: The CiC should rack-out smoothly without
mechanical interference. If any unusual
resistance is detected, stop immediately and
correct the situation before proceeding.
WARNING: THE CiC ADAPTER COULD DROP
DURING THIS OPERATION. FASTEN IT TO A
LIFTING TRUCK BEFORE PROCEEDING.
Ÿ Place the extended rails and lock them
with switchgear rails as shown in (fig. 11).
Ÿ Pull out the CiC adapter from switchgear cell
until they it is on extended rails as shown in (fig. 12).
Ÿ Lift the CiC adapter from the rails using the
designated lifting points with equipment that has
ratings which exceed the values listed in Table B
on page 1.
Fig. 9
2
Fig. 10
Fig. 11
Fig. 12
1

Advertisement

loading

This manual is also suitable for:

Emax 2Db-25Db-50E-1.2E-2.2