7.1.4
Further documents
Note
Further documents
Observe all of the other documents provided with this machine.
7.2
Setpoint values for monitoring the bearing temperature
Prior to commissioning
If the machine is equipped with bearing thermometers, set the temperature value for
disconnection on the monitoring equipment before the first machine run.
Table 7- 1
Set value
Alarm
Shutting down
Normal operation
Determine the maximum operating temperature of the bearings T
the temperature, bearing load and influences of the plant on the motor in °C. Set the values
for shutdown and warning corresponding to the operating temperature T
Table 7- 2
Set value
Alarm
Shutting down
7.3
Switching on
Measures for start-up
After installation or inspections, the following measures are recommended for normal start-
up of the machines:
● Start the machine without a load. To do this, close the circuit breaker and do not switch
the machine off prematurely. Switching the machine off again while it is starting up and
1MB..1/2/3/4 - shaft heights 63 ... 355
Operating Instructions, 06/2020, A5E44455710A
7.2 Setpoint values for monitoring the bearing temperature
Set values for monitoring the bearing temperatures before commissioning
Set values for monitoring the bearing temperatures
Commissioning
Temperature
115 °C
120 °C
taking into account
operation
.
op
Temperature
T
+ 5 K ≤ 115 °C
operation
T
+ 10 K ≤ 120 °C
operation
93