Installation
Gas leak detection
Plug into socket
13
Leak detection
Attention !
After the gas pipeline connection has been completed, the
leak detection test must be performed by registered gas
installer who employed by registered gas contractor.
Smear the suds on each connection part with a soft brush,
and then open the gas valve to check carefully if bubbles
appear, please close the gas valve immediately, and adjust
the air inlet connection until no bubbles appear.
Connection electrical source
The electrical source is fixed in the middle of bottom, when
you use it, please confirm it is safety and grounded.
Please confirm the hob wire are grounded, it is used attached
a tri-pins, and the tri-pins are grounded, when it is creepage,
the setting can prevent human from getting an electric shock.
We suggest the flashboard is fixed on the right underside, be
far away from the gas and air inlet.
size of tapping 700±2mm
surface
≈100mm
≈900mm