When you complete your work for the day, do the following:
1. Backfill the spoils in the part(s) of the trench in which
you are finished working.
2. Move the machine to a safe and stable location.
3. Move all levers to the Neutral position.
4. Engage the parking brake.
5. Lower all attachments to the ground.
6. Let the machine idle for a few moments to cool it
down.
7. Shut off the engine, wait for all moving part to stop,
and remove the ignition key.
8. Turn the battery disconnect switch to the Disconnect
position.

Completing the Project

1. After you complete the project, return the spoils back
into the trench with the backfill blade; refer to Using
the Backfill Blade (page 29).
2. Return the spoils into the trench.
A. Move the machine to the end of the trench, a few
feet (meters) away from the spoil pile.
B. Aim the machine at the outer edge of the pile.
C. Adjust the backfill blade to fit the slope of the
ground.
D. Move the outer edge of the spoil pile toward the
trench.
Note: Make at least 2 passes at the pile to move
it.
E. Repeat the steps above for the spoil pile on the
other side of the trench.
F. Float the backfill blade over the length of the
trench.
3. Spray the dirt and mud off the machine with water.
Note: Do not spray the console or electrical
components with water.
4. Transport the machine from the completed work site;
refer to Transporting the Machine (page 30).