Huawei UPS5000 User Manual

Top air-flow cabinet
Hide thumbs Also See for UPS5000:

Advertisement

Quick Links

UPS5000 Top Air-flow Cabinet
User Manual
Issue
02
Date
2022-01-19
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei UPS5000

  • Page 1 UPS5000 Top Air-flow Cabinet User Manual Issue Date 2022-01-19 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a hazard with a medium level of risk which, if not avoided, could result in death or serious injury. Indicates a hazard with a low level of risk which, if not avoided, could result in minor or moderate injury. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 4 Issue 02 (2022-01-19) Optimized the installation procedures. Issue 01 (2020-04-27) Added the isolation protection model. Issue Draft A (2016-12-09) This issue is used for first office application (FOA). Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    3.4.1 Connecting Cables to the Top Air-flow Cabinet Used for a Single-Cabinet UPS........24 3.4.2 Connecting Cables to the Top Air-flow Cabinets Used for a Multi-Cabinet UPS........31 4 User Settings.......................... 39 5 Replacing a Fan........................40 A Acronyms and Abbreviations..................... 43 Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 6: Safety Precautions

    ● Before installing the top air-flow cabinet, get tools insulated and remove conductive objects such as watches and rings. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 7: Product Overview

    ● 01: used for 600 mm wide cabinets ● 02: used for 800 mm wide cabinets ● Single-cabinet UPS: The UPS has only one cabinet. The following figure shows the installation position for the top air-flow cabinet. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 8 Four-cabinet UPS: The UPS has two power cabinets and two bypass cabinets. The following figure shows the installation positions for the top air-flow cabinets. Figure 2-4 Installation positions of the top air-flow cabinets for a four-cabinet Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 9: Structure

    Figure 2-5 Top air-flow cabinet structure (1) Fan transit unit (2) Fan transit unit (3) Fan interconnection protective cover terminal cover (4) Cable trough (5) Fan assemblies (6) Anchor bolts Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 10 UPS5000 Top Air-flow Cabinet User Manual 2 Product Overview Figure 2-6 Side view of the top air-flow cabinet (unit: mm) Figure 2-7 Side view of the top air-flow cabinet and UPS cabinet (unit: mm) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 11 Figure 2-8 Cable trough on the top air-flow cabinet (1) Fan power (2) 24-pin (3) Switch (4) Power switch ports (14-pin) terminal port protective cover Figure 2-9 Fan power port Figure 2-10 24-pin terminal port Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 12: Product Installation

    ● Check that the fittings comply with the packing list. If some fittings are missing or do not comply with the packing list, record the information and contact your local Huawei office immediately. 3.2 Installation Tools Table 3-1 lists the installation tools.
  • Page 13 Provide electrical insulation. Brush Clean panels and shells. Protective gloves Protect hands. ESD gloves Protect devices from ESD. Insulation gloves Provide insulation. Insulation protective shoes Protect operators. Cable tie Bind cables. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 14: Installation And Securing

    UPS and move them to the installation position. If the antiseismic kit is configured, secure it to the UPS first. Procedure Step 1 Remove the rear cover from the UPS cabinet. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 15 UPS5000 Top Air-flow Cabinet User Manual 3 Product Installation Figure 3-1 Removing the rear cover from the UPS cabinet Step 2 Remove the rear cover fasteners from the UPS cabinet. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 16 Step 4 Move the top air-flow cabinet to the rear of the UPS cabinet. Step 5 Adjust the four anchor bolts of the top air-flow cabinet to make it as high as the UPS cabinet. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 17 Top air-flow cabinet with a PC panel If the top air-flow cabinet with a PC panel needs to be combined with the UPS cabinet, remove the highest connection plate from the top air-flow cabinet. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 18 Step 7 (Optional) If the UPS is installed against a wall, reinstall the rear cover for the top air-flow cabinet, remove the left and right side panels from the top air-flow cabinet, and put the side panels away. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 19 UPS, secure the antiseismic kit to the ground from the side of the top air-flow cabinet. Step 9 Install the bottom plates. Figure 3-7 Installing the bottom plates ----End Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 20: Securing The Top Air-Flow Cabinets Used For A Multi-Cabinet Ups

    Figure 3-8 Dimensions of the channel steel for the top air-flow cabinets (unit: (1) Mounting hole for the channel (2) Anchor bolt of the top air-flow steel for the UPS cabinet cabinet Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 21 Step 2 Remove the fasteners from the rear covers and anchor baffle plates of the UPS cabinets. (For the 600 kVA model, remove the rear door headers and fasteners from the 800 mm wide cabinets.) Figure 3-9 Removing fasteners (400 kVA and 500 kVA cabinets) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 22 UPS5000 Top Air-flow Cabinet User Manual 3 Product Installation Figure 3-10 Removing fasteners (600 kVA cabinets) (1) 800 mm wide cabinet (2) 600 mm wide cabinet Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 23 Figure 3-11 Removing fasteners (800 kVA cabinets) Step 3 Install conversion brackets at the leftmost and rightmost anchors of the UPS. Figure 3-12 Installing conversion brackets (dual-cabinet, 400 kVA model used as an example) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 24 2 and 3, left side panel of top air-flow cabinet 1, and right side panel of top air-flow cabinet 4. Figure 3-15 Installation positions of the top air-flow cabinets for a four-cabinet Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 25 Figure 3-16 Removing the PC panel from the top air-flow cabinet Step 6 Remove the rear cover from the top air-flow cabinet and put the cover away. Figure 3-17 Removing the rear cover from the top air-flow cabinet Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 26 UPS cabinets. Step 9 Connect the top air-flow cabinets with the UPS cabinets, as shown in Figure 3-4 Figure 3-5. Step 10 Remove the bottom sealing plates from the top air-flow cabinets. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 27 If the antiseismic kit is configured for the UPS, secure the antiseismic kit to the ground from the side of the top air-flow cabinet. Step 14 Install the bottom plates for the top air-flow cabinets. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 28 3 Product Installation Figure 3-22 Installing bottom plates (400 kVA and 500 kVA cabinets) Figure 3-23 Installing bottom plates (600 kVA cabinets) Figure 3-24 Installing bottom plates (800 kVA cabinets) ----End Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 29: Cable Connection

    Step 3 Connect the power cable and signal cable of the top air-flow cabinet to the UPS. Pull out the power cable (04093521-07) from the cable trough of the top air- flow cabinet, bind the cable along the post of the top air-flow cabinet, and Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 30 – Each isolation protection model is illustrated. – M4 screws should be used and tightened to 1.4 N·m. Figure 3-27 Connecting the power cable of the top air-flow cabinet to the UPS (300K-SM) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 31 Figure 3-28 Connecting the power cable of the top air-flow cabinet to the UPS (300K-SMT, isolation protection) Figure 3-29 Connecting the power cable of the top air-flow cabinet to the UPS (200K-FM) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 32 UPS (120K-FM, isolation protection) Connect the signal cable (04093521-01) of the top air-flow cabinet routed out from the fan transit unit to the J23 and J29 ports on the UPS parallel board. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 33 Figure 3-32 Connecting the power cable and signal cable of the top air-flow cabinet (300K-SM) Figure 3-33 Connecting the power cable and signal cable of the top air-flow cabinet (300K-SMT, isolation protection) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 34 UPS5000 Top Air-flow Cabinet User Manual 3 Product Installation Figure 3-34 Connecting the signal cable of the top air-flow cabinet (200K- Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 35 Figure 3-36 Connecting the signal cable of the top air-flow cabinet (120K-FM, isolation protection) Step 4 Take out cable trough side panels from the fitting bag and install them on the two sides of the cable trough of the top air-flow cabinet. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 36: Connecting Cables To The Top Air-Flow Cabinets Used For A Multi-Cabinet Ups

    Figure 3-38 Removing the cable trough covers and fan interconnection terminal protective covers Step 2 Connect the ground cable of each top air-flow cabinet to the nearest beam of the UPS cabinet. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 37 Signal cable connection method: Connect the signal cable (04093521-01) of the top air-flow cabinet routed out from the fan transit unit to the J23 and J29 ports on the UPS parallel board respectively. ● 400K-FM cabling mode Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 38 UPS5000 Top Air-flow Cabinet User Manual 3 Product Installation Figure 3-40 Connecting the power cable and signal cable of the top air-flow cabinet (400K-FM) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 39 UPS5000 Top Air-flow Cabinet User Manual 3 Product Installation Figure 3-41 Connecting the power cable of the top air-flow cabinet to the UPS (400K-FM) ● 800K-FM cabling mode Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 40 3 Product Installation Figure 3-42 Connecting the power cable and signal cable of the top air-flow cabinet (800K-FM) Figure 3-43 Connecting the power cable of the top air-flow cabinet to the UPS (800K-FM) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 41 Figure 3-44 Removing a short-circuit terminal from the fan power port Step 5 Connect fan power cables to each top air-flow cabinet. NO TE The 24-pin terminal cables can be connected to any 14-pin terminal in top air-flow cabinet Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 42 UPS5000 Top Air-flow Cabinet User Manual 3 Product Installation Figure 3-45 Connecting fan power cables (400K-FM) Figure 3-46 Connecting fan power cables (400K-FM) Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 43 Step 7 Reinstall the fan interconnection terminals protective cover and rear cover or side panels of the top air-flow cabinets. ----End Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 44: User Settings

    Step 2 Remove the power switch protective cover from the top air-flow cabinet. Figure 4-2 Removing the power switch protective cover Step 3 Turn on the switch of the top air-flow cabinet and reinstall the protective cover. ----End Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 45: Replacing A Fan

    Step 1 Remove the power switch protective cover and turn off the switch. Figure 5-1 Removing the power switch protective cover Step 2 Remove the fan interconnection terminal cover. Step 3 Remove the two interconnection terminals (FanXP and FanXS) from the faulty fan. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 46 Figure 5-2 Removing the interconnection terminals Step 4 Take out the fan assembly. Figure 5-3 Taking out the fan assembly Step 5 Remove the faulty fan and install a normal fan. Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 47 Step 7 Reconnect the two interconnection terminals (FanXP and FanXS) of the fan and reinstall the fan interconnection terminal cover. Step 8 Turn on the power switch and reinstall the power switch protective cover. ----End Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.
  • Page 48: A Acronyms And Abbreviations

    UPS5000 Top Air-flow Cabinet User Manual A Acronyms and Abbreviations Acronyms and Abbreviations uninterruptible power system Issue 02 (2022-01-19) Copyright © Huawei Technologies Co., Ltd.