PCS100 AVC-40 Commissioning Checklist
—
Document Information
Copyright notice
The information in this manual is subject to change without notice. This manual and parts thereof must not be re-
produced or copied, or disclosed to third parties, nor used for any unauthorized purpose without written permis-
sion from ABB Ltd. The hardware and software described in this manual are provided under a license and may be
used, copied, or disclosed only in accordance with the terms of such license.
Document identification
Ownership: ABB Ltd., Power Conditioning Products
Document number: 2UCD740000E004
Issue date: 13/12/2021
Revision: Rev G
Contact information
Address: ABB Ltd. 111 Main North Road, Napier, New Zealand.
Website: https://new.abb.com/ups
This Document
This document contains information regarding:
commissioning of the PCS100 AVC-40
–
Usage
This document should be used when:
commissioning the PCS100 AVC-40
–
Who Should Read This Document?
This document is intended for:
commissioning engineers
–
Prerequisites
A Commissioning Engineer working with the PCS100 AVC-40 must:
be trained by ABB and have electrical operational and safety knowledge
–
have sufficient training to operate in an accidentally touch safe serv ice environment
–
use this document in conjunction with the PCS100 AVC-40 User Manual and PCS100 AVC-40
–
Installation Checklist and ensure all of the installation checks have been performed prior to
completing this checklist
Software Revision
This document applies to PCS100 AVC-40 systems with software revision R2J4.
3