PCS100 AVC-40 Commissioning Checklist

Commissioning Checklist

The following commissioning checklist for the PCS100 AVC-40 is required to be completed and signed off by a
suitably qualified engineer who has been trained in the use of power systems, electrical safety and the PCS100
AVC-40 products.
Company:
Site:
PCS100 AVC-40 Model:
PCS100 AVC-40Serial Number:
Engineer:
Before proceeding with this commissioning schedule, the Commissioning Engineer should be familiar with the
following:
accessing and navigating within the menu, including the commissioning section, on the GDM
adjusting system parameters on the GDM
starting and stopping the PCS100 AVC-40 via the GDM

1.1 Pre-Power Visual Checks

No
Description
1.
Check power to the unit is safely isolated and locked off.
2.
Confirm power is isolated with a meter check.
3.
Visual check mechanical installation.
4.
Check there is no physical damage to unit and internal parts.
5.
Check no debris, swarf or wire strands are present.
6.
Check there is no insulation damage or signs of exposure to water or conductive dust
during transport and storage.
7.
Check the clearances between terminals, cables, bolts, and lugs are appropriate.
Ideally the main supply and load power terminations at the transformer should be fully
insulated.
8.
Check the supply and load cable or buswork used is adequate for PCS100 AVC-40 load
rating.
9.
Check all rectifier and inverter modules are correctly connected to the power wiring
and the communications and control ribbon cable is fully bedded.