6.5 Debugging and running

6.5.1 Confirm the project before running
Unit power supply. Be sure to have the same power source as the product nameplate.
The circuit connection of the unit. Check the wire diameter and wiring of the power supply wire, and the ground
wire is firmly connected. Check if the linkage of the pump or the like is properly connected.
Water pipes and pipes. Water pipes and pipes must be flushed at least two or three times to ensure cleanliness
without any contaminants.
Check the water circulation system. Check that the water volume is sufficient, that the air is drained, and that
there is no leakage.
When powering on for the first time or after a long time of shutdown, the power must be turned on in advance to
heat the crankcase for at least 2 hours.
The water filter is installed in place as required, and there is no pollutant in the water filter.
Water flow switch, the pump overload has been linked with the unit, and the drain valve has been installed in
place.
6.5.2 Check of running status
After the unit is running smoothly, check the following items:
Number
1
2
Operating current of a single compressor
3
Operating current of a single fan
Unit inlet water temperature during cooling
4
Unit outlet water temperature during
5
Unit inlet water temperature during cooling
6
Unit outlet water temperature during
7
8
Inlet and out water temperature difference
9
Compressor exhaust temperature
10
Low pressure during cooling operation
11
High pressure during cooling operatio
12
Low pressure during heating operation
13
High pressure during heating operatio
14
Remarks: The judgment reference standard is only the basis for the normal operation of the on-site unit.
The highest and lowest values of the reference standard are judged as the reference standard for the maximum
working condition and the minimum working condition of the unit. If the unit is stable and exceeds the reference
standard, please consult your local dealer and Haier for sale.
Check item
Voltage
operatio
cooling operation
operatio
cooling operation
Vibration, running sound
Inspection essential
Voltmeter confirmation
Galvanometer confirmation
Galvanometer confirmation
Thermometer confirmatio
Thermometer confirmatio
Thermometer confirmatio
Thermometer confirmatio
Thermometer confirmatio
Thermometer confirmatio
Pressure gauge confirmation
Pressure gauge confirmation
Pressure gauge confirmation
Pressure gauge confirmation
Auscultation or palpatio
26
Judging reference
standar
±10% of rated voltage
6~23A
0.2~3.6A
8~28°C
5~21°C
24~50°C
29~55°C
2~8°C
35~105°C
6.5~12.0bar
14~36.5bar
2~12.5bar
18~36.5bar
No abnormal vibration,
running sound