ESS-240V12-(9AhBPVBA04, 7AhBPVBA04) Battery
Pack
Quick Guide
Connecting Cables to Battery Packs for a Single UPS2000-G-6 kVA/10 kVA
Figure 3-14 Connecting cables to battery packs for a single UPS2000-G-6 kVA/10
kVA
Connecting Cables to Battery Packs for a UPS2000-G-6 kVA/10 kVA Parallel
System
Issue 01 (2021-12-23)
NO TE
The following wiring diagram uses a standard UPS with one battery pack as an example.
NO TE
1. The following wiring diagram uses each standard UPS with one battery pack as an
example.
2. If the number of 6 kVA/10 kVA UPSs in a parallel system is greater than or equal to
three, each UPS can be configured with a maximum of four battery packs. The cable
connection methods for each UPS and battery pack are the same as those for a single
UPS.
Copyright © Huawei Digital Power Technologies Co., Ltd.
3 Installation