Step 4 – Connect DC Output
Connections are under rear covers.
Bus Connection - to adjacent shelf
Install inter-shelf buses joining -48V and RETURN outputs of
adjacent shelves. Torque to 65 in-lb (7.3 Nm)
Cable Connection
Output current: 200A max
Wire size: 2/0AWG
Connect cables with suitable lugs to -48V and RETURN.
Torque to 65 in-lb. (7.3 Nm)
Lug Landings - 2 x 1/4" on 5/8" center, 0.7" (18mm) max.
tongue width.
Caution:
Verify battery voltage and polarity with a voltmeter
before proceeding.
Note:
RETURN must be externally connected to DC
Reference (CO) ground.
Step 5 – Connect Shelf to Shelf Cables
Install Data cables between adjacent rectifier shelves - J3-4.
Install Distribution Cable between the distribution shelf and the adjacent L051C shelf - J7
Distribution cable
Step 6 – Set Shelf ID Jumpers
Up to 4 Rectifier Shelves can be interconnected. Each Rectifier Shelf must have a unique ID.
L051C
set to 1
1st set to 2
Step 7 – Set Controller Jumpers
LAN port may be temporarily set to Local mode,
but must be set to Network mode for remote
monitoring.
Alarm relays may be set to "Open on Alarm" or "Close on
Alarm".
Page 8
2023 ABB. All rights reserved.
Data cable
Shelf ID
L052C
2nd set to 3
3rd set to 4
SPS Shelf L051C_L052C_QSG
Cable Connection
Dual Lug Landings
L051C Shelf (ID=1)
(with controller)
1st L052C Shelf (ID=2)
(no controller)
Local/Network jumper
USB Craft Port
-48V Connections
RETURN Connections
covers removed
covers shown
2 Adjacent Shelves
Distribution Shelf
Alarm relay jumpers
Rev 5.0