Nec Responsibilities - NEC Express5800 1080Xd User Manual

Hide thumbs Also See for Express5800 1080Xd:
Table of Contents

Advertisement

If your Server is to be installed in an existing computer room, you should analyze and
integrate the following items into the site plan:
Available space
!
Additional environmental requirements
!
Additional electrical requirements.
!

NEC Responsibilities

NEC will install your Express5800/1000 Series server, including:
Moving all server cabinet containers and accessory boxes shipped with the server
!
to the intended installation site
Unpacking the Express5800/1000 Series server and any accessory boxes
!
Inspecting the server for any shipping damage
!
Installing all accessory components including hard disk drives and cabinet
!
stabilizers
Powering up, configuring and running server test/diagnostics.
!
Express5800/1080Xd/1160Xd/1320Xd Site Preparation Guide 5

Advertisement

Table of Contents
loading

Table of Contents