14

TEST RUN CHECK

14-1.Check Items Before Trial Run
No.
1
Has the electrical work (power supply and communication wiring work) been completed?
1.When the Energy Monitoring Relay Interface or Digital Input / Output Relay Interface is connected, check that the
polarity (A / B) of the wiring is correct.
2.Check that the terminal resistance has been set.
3.When a custom device is connected, check that the TCC-LINK adaptor has been connected.
2
Has the addresses of the air conditioner (Indoor units (DN=03, 12, 13, 14)) and outdoor unit (outdoor unit control board
switch 13 / 14) been set?
1.Check that the address of the general device interface has been set.
3
Has the setting file been created?
4
Have the controller switch and DN been set?
5
Has the controller IP address been checked?
6
Have the network and the browser proxy of the PC to be connected been set?
7
Are all the devices turned on?
When the power distribution function is used:
8
Is the Monthly Report Creation Software installed?
9
Is the network setting completed for the PC where the Monthly Report Creation Software is installed?
Check item
Key point
Key point