Installing the Cabinet
Planning the Installation
Before installing the common equipment, you should mount a Main Distribution Frame (MDF) plywood
backboard in a centrally located spot. A 1/2 sheet of plywood (4' x 4') should be more than adequate (see
Figure 1-1 Installation Layout below). Mount this backboard using suitable fasteners, taking care to adhere
to standard installation practices and local codes.
The equipment cabinet requires a three-prong, dedicated 110 VAC 60 Hz circuit (NEMA 5-15 receptacle)
located within 4 1/2' feet of the cabinet's lower left corner.
Normally, you install the extension blocks and trunk/AUX jacks to the right of the Main Cabinet.
•
•
DS1000 Hardware Manual
Local codes may prohibit you from installing extensions, trunks and optional equipment in
the same blocks.
Do not plug in the 25-pair extension cable with power applied.
To telco
ground
Surge
Protector
Figure 1-1: Installation Layout
Installing the Cabinet
!! Important !!
Plywood backboard
4'
Trunk/AUX
RJ-25C Jacks
Station
Blocks
Dedicated
AC Outlet
Section 1: Installation Basics ◆ 1-5
4'
1