Commissioning
3.3

Commissioning after taking out of operation

If present
Remove cover plates (blind flanges) from the compressor casing, the gas inlet and the gas
outlet.
Version with compressor wheel cooling:
Remove the locking screw on the cooling air connection and fit the cooling air line.
General
Check the exhaust gas pipe before and after the turbine for combustion residues or water
residues and clean it. Remove any foreign objects that may be present.
Check and clean filter silencer or air supply line, and remove any foreign objects that may
be present.
Put engine-side oil circulation to the turbocharger into operation.
Prepare the turbocharger for operation according to section "Checks before commission-
ing".
The turbocharger is now ready for operation.