Installation Procedure

Installation Procedure
1
Unpack all items and check
for damaged or missing parts.
See page 8 for details.
2
Install the trunk card
See page 9 for details.
3
Install the CPU card
See page 9 for details.
4
Mount the SL2100 system on
the wall or in the rack
See page 15 for details.
5
Connect the telephones.
6
Connect the External MOH
Device.
7
Connect the exchange lines.
See page 1918 for details.
8
Connect the power and switch
on the SL2100.
See page 20 for details.
9
Configure the SL2100 to the
customer's requirements.
See page 2121 for details.
10
Security
!
Consider the operation during
power failure

Power Fail Operation

It is not possible to have power fail operation with ISDN PRI trunks.
If power fail operation is required by the customer then it is recommended that additional analogue trunks are
installed.
Quick Install Guide – SL2100 with ISDN PRI Trunks rev 1.1
! Within suitable cabling distance from the exchange lines.
! Within suitable distance from a power socket and Earth point.
! Check the other installation considerations in section 3.
See separate Quick Install Guide for the terminal type being installed
Optional
See separate Quick Install Guide for the terminal type being installed
Use SL2100 PCPro software
Ensure the system is protected against Toll Fraud and has secure
maintenance passwords
Will require additional parts if required for a PRI system