Dc Requirements; Redundancy; Cable And Connector Requirements - Dell Force10 E300 Installing And Maintaining

Hide thumbs Also See for Force10 E300:
Table of Contents

Advertisement

Figure 5-2. DC PEM Locations
Air Filter

DC Requirements

Maximum Power Dissipation
Maximum DC PEM Input Current

Redundancy

For full facility redundancy, install two DC PEMs where each PEM must be attached to an independent
power source with a dedicated circuit breaker sized in accordance with your local building and electrical
safety codes.

Cable and Connector Requirements

You must provide your own cables to connect to a remote power source (a circuit breaker panel, for
example) in your equipment rack or facility. Cables must be sized to meet the following criteria:
• Rated for 60A service to allow for a fully loaded E300 system per NEC in the United States or
internationally, per local safety codes.
• Limit voltage drop across the cable length to 0.5V or less.
Before you make the cable connections, apply a coat of anti-oxidant paste to unplated metal contact
surfaces. File unplated connectors, braided straps, and bus bars to a shiny finish. It is not necessary to file
and coat tinned, solder-plated, or silver-plated connectors or other plated connection surfaces, such as
those on the PEM studs.
NOTE: Please take precautions against over-tightening the screws or nuts on this device.
DC Power Supply
Slot 0
DC Power Supply
Slot 1
fn00121cHH
Optional Grounding
Holes
2400W
60A
Installing Power Modules
|