Download Print this page

Huawei V100R001C00 Quick Installation Manual

Micro dc
Hide thumbs Also See for V100R001C00:

Advertisement

Quick Links

HUAWEI Micro DC V100R001C00
Quick Installation Guide
Issue: 01
BOM: 31505829
Release Date: 2013-03-06
This document helps the customer service personnel quickly install the Micro data center (DC). For details, see the product
document CD-ROM delivered with the product.
Required Tools
Installation Process
 Devices delivered to customers consist of typical configuration suite and extension components. The installation of extension
components varies with the number of terminals to be supported, while the installation of the typical configuration suite remains
unchanged. The Micro DC applies to scenarios in which 150, 300, and 600 terminals are supported.
 If customers require more than 1 hour backup power, install a battery cabinet.
Cabinet installation process for 150 terminals
Cabinet installation process for 300 and 600 terminals
Copyright © Huawei Technologies Co., Ltd. 2013. All rights reserved.
1

Advertisement

loading

Summary of Contents for Huawei V100R001C00

  • Page 1 The Micro DC applies to scenarios in which 150, 300, and 600 terminals are supported.  If customers require more than 1 hour backup power, install a battery cabinet. Cabinet installation process for 150 terminals Cabinet installation process for 300 and 600 terminals Copyright © Huawei Technologies Co., Ltd. 2013. All rights reserved.
  • Page 2 Checking Quantities and Types of Goods Number of Device Type Device Quantity Remarks terminals 1 AR2220, 1 S5752, 3 S3752s, 1 PDB, 1 UPS (6 kVA), 1 PDU, 1 Typical Micro DC All-in-One cabinet fan assembly, and 1 monitoring system (including 1 ECC, 1 configuratio temperature and humidity sensor, 1 water leakage sensor, 2 door n suite...
  • Page 3 Installation Planning For 150 terminals All-in-One cabinet...
  • Page 4 Installation Planning For 300 terminals Network distribution cabinet (front view) 42 1U 1U 42 41 1U 1U 41 40 1U 1U 40 39 1U 1U 39 38 1U 1U 38 37 1U 1U 37 36 1U 1U 36 35 1U 1U 35 34 1U 1U 34...
  • Page 5 Installation Planning For 600 terminals Network distribution cabinet (front view) 42 1U 1U 42 41 1U 1U 41 40 1U 1U 40 39 1U 1U 39 38 1U 1U 38 37 1U 1U 37 36 1U 1U 36 35 1U 1U 35 34 1U 1U 34...
  • Page 6 Labeling Labeling for Network Devices  The rack is divided into 42 U (1 U = 1.75 in.), numbering from 1 to 42 from the bottom up.  For the network device occupying more than 1 U, the label records the smallest height number. For example, if a 2 U network device occupies 34 U and 35 U, "34U"...
  • Page 7 Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > Installing the All-in-One cabinet (for All Scenarios) Remove reinforcing brackets from Combine and level cabinets. the cabinet. There is one reinforcing bracket at the height of 22 U (38.5 in.) in the front and rear of the cabinet.
  • Page 8: Gprs Module

    Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > Installing the All-in-One Cabinet > (Optional) Installing the SIM Card (for All Scenarios) Install the subscriber identity module (SIM) Remove the General Packet Radio Service card.
  • Page 9 Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > (Optional) Installing Battery Packs (for All Scenarios) Positions for installing Battery Packs If customers require more than 1 hour backup power, install a battery cabinet or battery packs. ...
  • Page 10 Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > Installing Servers (for All Scenarios)  Only one RH2288 is provided by default for Micro DC typical configurations for 150, 300, and 600 terminals. ...
  • Page 11 Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > Installing Extension Components > Installing the Integrated Sensor Mounting Arm (for All Scenarios) Securing the sensor mounting arm  Two persons are required to install the sensor mounting arm with the help of a step ladder. ...
  • Page 12 Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > Installing Extension Components > Installing the Integrated Sensor Mounting Arm (for All Scenarios) Connect a signal cable for the smoke sensor. Insert the signal cable connector into the correct position on the transfer board.
  • Page 13  If customers require more than 1 hour backup power, install a battery cabinet.  The battery cabinet is installed in the same way as the All-in-One cabinet.  For details about how to install batteries, see the Micro DC V100R001C00 Installation and Operation Guide.
  • Page 14 Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > Installing Extension Components > Inspecting Devices Before Power-On Inspecting the PDB  Commissioning mechanical performance 1. Switch on and off all circuit breakers five times. Ensure that they can be switched on and off smoothly. 2.
  • Page 15: Ups Front Panel

    Checking Quantities and Types of Goods > Inspecting Goods > Installing the Typical Configuration Suite > Installing Extension Components > Inspecting Devices Before Power-on > Performing Power-On and Power-Off Tests UPS front panel Circuit breaker on the battery pack PDU input circuit breaker Input circuit breaker on the UPS backplane...
  • Page 16: Power-On Process

    4. Keep the UPS running without loads for 10 minutes. Shutting down the UPS Press on the UPS panel to shut down the UPS. Huawei Technologies Co., Ltd. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China http://enterprise.huawei.com...