Download Print this page
Huawei PowerCube 500 Manual
Hide thumbs Also See for PowerCube 500:

Advertisement

Quick Links

PowerCube 500 V200R001C00 Quick Guide (ICC50)
Issue: 03
Date: 2018-06-20
1
Product Overview
Solar+Mains Scenario
Lightning rod
PV module
PV module
support
Cantilever
CPE
Barrel
camera
Dome
camera
Pole
ICC Interior
Space for transmission equipment
Network port SPD
Space for a PDU
Space for an inverter
DCDU-80A1
Space for ESMU
Space for batteries
Mains Scenario
Barrel
camera
Cantilever
Dome
camera
ICC50
Copyright © Huawei Technologies Co., Ltd. 2018. All rights reserved.
Cable Holes on the Pole
CPE cable and PV
Lightning rod
CPE
camera
ICC50
Support
Pole (a cabinet
can be installed on
the pole with BOM
number 21540285)
Mains AC cable,
optical fiber, ICC
ground cable,
camera cable,
CPE cable, and
PV module cable
1
module cable
Dome
Barrel
camera
cable
cable
ICC ground
cable
PoE
Heater

Advertisement

loading

Summary of Contents for Huawei PowerCube 500

  • Page 1 PowerCube 500 V200R001C00 Quick Guide (ICC50) Issue: 03 Date: 2018-06-20 Copyright © Huawei Technologies Co., Ltd. 2018. All rights reserved. Product Overview Solar+Mains Scenario Mains Scenario Cable Holes on the Pole CPE cable and PV Lightning rod Lightning rod Barrel...
  • Page 2 Cable Holes on the Partition Plate Bottom Cable Holes E-label cable, ESMU-battery signal cable Ground cable, AC cable, Ground Optical fiber, signal cable, optical fiber, PV DC cable cable DC cable and PV DC cable, Signal cable hydrogen DC cable and signal Signal discharge tube...
  • Page 3 Installing a Camera and Cables Installing a Camera For the camera installation method, see the documents delivered with the equipment. Installing Camera Cables For the cable connections at the camera side, see the documents delivered with the equipment. Reserve the other ends of cables. Installing PV Modules and Cables Installing a PV Module Support In the northern hemisphere, PV modules face south.
  • Page 4 Installing PV Modules Installing Two PV Modules 1. Install PV modules. 2. Install cables for the PV modules. Adhesive tape Installing Four PV Modules 1. Install vertical beams. 2. Install supports. 3. Install PV modules. 4. Install cables for the PV modules. Adhesive tape...
  • Page 5 Installing a Lightning Rod Solar+Mains Scenario Mains Scenario Adjust the tilting angle of the lightning rod according to the site latitude. Site Lightning Latitude Rod Tilt (Degree) Angle 0–15 15° 16–25 25° 26–30 35° 31–45 45° Pole 1. Install mains AC input 2.
  • Page 6: Installing Components

    3. Install the ICC ground cable. ICC ground cable Installing Components Installing Modules M48300N1 PSU slot PSU slot S4820G slot PSU slots support the installation of the R4850G2 and  R4850N6.  The PSU, S4820G, and M48300N1 are installed in the same way.
  • Page 7 Installing an MA5671 Router Installing an NE05E-SK Router When installing the NE05E- SK router, remove the small tray and install the NE05E- SK on the big tray. Installing an AR531 Router 4. Install the router communications cable. 5. Install router power cables. Router power port Router Installing a Network Port SPD and Cables...
  • Page 8 3. Install cables between the inverter and PDU. 4. Install the alarm cable and power cables for the inverter. Installing a PoE and Cables 1. Install the PoE and its power cables. 2. Install the PoE signal cable. Camera Router The router is optional.
  • Page 9 Installing Batteries and Battery Cables 10.1 Installing Lead-Acid Batteries and Cables Installing the TCB-60C and Cables 3. Install the two 1. Install cables at battery terminals. 2. Remove the battery baffle bars. inner batteries and reinstall the battery baffle bars. 5.
  • Page 10 4. Install battery cables. 5. Install a hydrogen discharge tube. Routing the hydrogen discharge tube out of the cabinet 10.2 Installing Lithium Batteries and Cables (ESU-A2400Wh/D) 1. Turn off the energy storage management unit (ESMU) 2. Set the ESMU address using the DIP switch and CAN DIP switch. power switch and install the ESMU and ESU-A.
  • Page 11 7. Install the positive ESU-A power cables. 10.3 Installing Lithium Batteries and Cables (ESM-4850A1, ESM-4875A1) 1. Install ESM-4850A1/ESM-4875A1. 2. Install a battery ground cable. TO the nearest ground blot TO the nearest ground blot 3. Install the ESM signal cables. 4.
  • Page 12: Power-On Commissioning

    5. Install battery activation cables. The other end of the activation cables are connected before delivery. Preparing for Power-On Switch off the battery circuit breaker, load  circuit breaker, AC input circuit breaker, and M48300N1 circuit breaker. Verify the battery cable connections. ...
  • Page 13 Primary IP Network NetEco Comm. Parameters 192.168.0.10 Set an IP address for the standby NetEco server. Parameters Backup IP NetEco Port Please contact Huawei technical support if you 31220 Number need change the port number. Battery Parameters Basic Rated Set the parameter based on the actual battery...
  • Page 14 6. Slide the sliding cover back. Huawei Technologies Co., Ltd. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China www.huawei.com...

This manual is also suitable for:

Icc50