Installation Preparations

Wear gloves during installation.
Never install a module with power on. Ensure that the angle between a module and the line vertical to the ground is within 10degrees.
Do not assemble a lithium battery with an RRU. Do not install a PSU on the left side of an RRU or lithium battery.
The paint on the module exterior should be intact. If paint flakes off, repaint the area to avoid corrosion.
An upstream AC SPD of at least 30 kA is required for the PSU.
When securing a large-pole mounting kit, ensure that the hoops are closely attached to the pole and that there are no sundries between the
hoops and the pole.
When the PSU is assembled with the RRU or lithium battery, ensure that the PSU, RRU, and lithium battery are installed in thesame direction
and that the handles are on the same side.
After unpacking the equipment, you must power it on within 24 hours. When the equipment is maintained, the power-off duration cannot
exceed 24 hours.
If a lithium battery sunshade is configured, install the sunshade on the outer side of the lithium battery after installing t h e PSU and lithium
battery.
(Unit: mm)
PSU
Lithium Battery
Lithium Battery
1 Sector/1 Frequency + 2 PSU
Lithium Battery
PSU
2
(Unit: mm)
4 PSU + 8 Lithium Battery
(Unit: mm)
PSU
PSU