PDU8000 Modular Precision Power Distribution Cabinet
User Manual (1100 mm Deep)
5.1 Site Requirements
The PDC site requirements are as follows:
5.2 Installation Preparations
Before installation, unpack and check the product, make available all required technical
documents, tools, and materials, check the installation environment, and train onsite
installation personnel.
5.2.1 Obtaining Technical Documents
Table 5-1 Technical documents
Technical Document
Schematic diagram
Issue 01 (2019-02-25)
Far away from dust, smoke, harmful gas, and corrosive, flammable, or explosive objects.
Free of interference from strong electromagnetic fields.
Cabling space should be planned for the site, and cable ladders and cable trays should be
designed for the PDC installation position.
The levelness error of the concrete pad must be less than 10 mm.
The power grid must meet the PDC input rating requirements.
Class C surge protection must be provided.
Temperature: –5° C to +40° C
Humidity: 5%–90% RH
Altitude: < 2000 m (derated when the altitude exceeds 2000 m). For the derating details,
contact Huawei technical support.
Copyright © Huawei Technologies Co., Ltd.
5
Installation Guide
Function
Describes the control
relationship of circuit
breakers for the PDC.
5 Installation Guide
Obtaining Method
Delivered with the product.
32