3.2. Installation steps
The following illustrations show possible assembly of the BEKOMAT
NOTE
Assembly instructions
•
•
•
•
•
•
•
E
BEKOMAT
8/9
®
Install a separate BEKOMAT
Do not use any tapered threaded joints.
Keep pipe length as short as possible.
Do not fit a filter/dirt trap into the condensate inlet.
Only use ball valves for the condensate inlet.
The venting line must be above the max. possible condensate level.
Observe minimum assembly heights
Installation BEKOMAT
A
B
8/9.
®
at each point where condensate occurs.
®
8/9
®
Venting A:
Install line ≥ 3/4" with ball valve
Condensate inlet B:
Install pipe ≥ 2" (DN 50) with flange and ball valve:
•
Short feed line!
•
Slope of the condensate inlet > 1 %!
•
No filter in the condensate inlet!
Condensate discharge C:
Install line ≥ 1"
(≥ 2" for BEKOMAT
•
Do not route into a manifold!
•
Max. 5 m incline!
C
•
The minimum operating pressure increases by 0.1 bar
per metre of incline!
For maintenance purposes:
Manual condensate drain D:
•
Install ≥ 3/4" with ball valve
Bypass line E:
•
Install ≥ 1" with ball valve
D
Installation and operation manual
9):
®