S15 Application Note 1.8.0
Startup Guide
Setup and program the basic parameters.
A
STEP
Startup Checklist
Visual Inspection
No foreign materials (metal shavings, hardware)
□
Input and Output Wiring
Input leads are not wired to output terminals
□
Input, output and control wires are in separate conduit
□
Motor leads do not share conduit with any other motor leads
□
Verify input and output wire tightness and condition (continuity, frayed wires, loose connections,
□
pinched insulation)
Motor Terminal Box
Verify no power factor correction capacitors are installed
□
Verify wire tightness and condition (continuity, frayed wires, loose connections, pinched insulation)
□
Drive to Motor Ground Connection (ASD chassis to motor chassis)
Verify wire tightness and condition (continuity, frayed wires, loose connections, pinched insulation)
□
Record the Electrical Distribution System
Delta/Wye with Grounded Secondary
Grounding Capacitor
□ Enabled □ Disabled
This should be
DISABLED
otherwise it could result in a VFD failure. Refer to Section 1.3.3 of the S15 Instruction Manual E6582175
for more details.
© Toshiba International Corporation 2021 www.toshiba.com/tic Email: TIC-ASD@toshiba.com (855) 803-7089 13131 West Little York Road, Houston, TX
on Ungrounded, Corner Grounded or High Impedance Grounding Systems
Estimated Time: 20-30 Minutes
Level: 1
Prerequisite:
•
S15 Application Note 1.1.0
Navigating Menus & Parameters