1.4 Example project for central I/O expansion

The following steps show how to set-up an application project and configure the hardware. A
simple logic is used as example to introduce in programming and commissioning of the PLC.
The workflow for creation of a visualization is explained, as well as how to set-up a webserver
for visualization.

1.4.1 Preconditions

Automation Builder is installed and licensed as, at least, basic edition
neering software Automation Builder" on page 3.
AC500 V3 CPU is assembled and connected to the PC.

1.4.2 Create, set-up and save your AC500 V3 project

1.4.2.1
Create a project
1.
2.
12
Plug the appropriate electronic and I/O modules in the correct locations (processor
module, communication modules on terminal base, and eventually also communication
interface modules and I/O modules onto dedicated terminal units).
Connect a programming cable (Ethernet cable between ETH port of CPU and PC with
engineering software).
Launch Automation Builder either out of the desktop icon or out of the Windows menu.
Select "New Project" or go to menu "File è New Project".