Download Print this page
Huawei SmartLi-512V-162Ah-F Quick Manual
Huawei SmartLi-512V-162Ah-F Quick Manual

Huawei SmartLi-512V-162Ah-F Quick Manual

Advertisement

Quick Links

01
Installation Preparations
1. Before installation, read the user manual carefully to get familiar with product information and safety
precautions.
2. Use insulated tools during installation and operations.
3. Only qualified professionals or trained personnel are allowed to install, commission, and maintain the
battery cabinet. Otherwise, personal injury or equipment damage may occur, and the caused battery
cabinet damage is not covered under any warranty or service agreement.
1. If the battery cabinet is installed but not powered on, manually powered off, or discharged, avoid
keeping it at low SOC for an extended period. Recharge the battery cabinet in a timely manner
according to the instructions in "Power-On Commissioning > Recharge Requirements for Batteries with
Low SOC" in the user manual. Otherwise, batteries may be damaged due to overdischarge.
2. It is recommended that an independent battery room be used. Before installing battery modules,
prepare fire extinguishing facilities, such as firefighting sands and liquid carbon dioxide fire
extinguishers, according to the construction regulations. Before operation, ensure that the battery room
is equipped with a fire extinguishing system that complies with local regulations.
Model
Weight
SmartLi-512V-162Ah-F
< 1100 kg
SmartLi-512V-162Ah-S
7+7, 7+0, 8+8, and 8+0 Scenarios
Output
Item
Power/Cabinet ≤
200 kW
Recommended cable
+/(N)/-
150
Battery
size (mm
2
)
PE
70
Connection mode: cable crimped with a DT terminal
Bolt specifications for +/N/-: M16x50 mm (120 N· m); bolt specifications for PE: M12x30 mm (47 N· m)
The bolt specifications in the table apply only to one end of the SmartLi cable. For details about the bolt specifications
for the other end, see the corresponding UPS manual.
6+6 and 6+0 Scenarios
Output
Item
Power/Cabinet ≤
170 kW
+/(N)/-
150
Recommended cable
Battery
2
size (mm
)
PE
70
Connection mode: cable crimped with a DT terminal
Bolt specifications for +/N/-: M16x50 mm (120 N· m); bolt specifications for PE: M12x30 mm (47 N· m)
The bolt specifications in the table apply only to one end of the SmartLi cable. For details about the bolt specifications
for the other end, see the corresponding UPS manual.
Appearance
Air vent
Communications cable outlet
Incoming cable glands
Battery circuit breaker
Monitoring interface unit
BCU
MDU
Fuse
Carbon
monoxide
gas sensor
(optional)
Document holder
MCCB
auxiliary
Slots for installing
lever
battery modules
Carbon
monoxide
gas sensor
(optional)
SmartLi 3.0 Quick Guide (Short-Term Backup Power)
02
Installing Cabinets
Unpacking
Removing the Pallet
Do not transport a
Configuration Type
cabinet with
With an LCD (master cabinet)
battery modules
Without an LCD (slave cabinet)
installed. If the
cabinet needs to
be transported or
moved, remove
200 kW < Output
250 kW < Output
the battery
Power/Cabinet ≤ 250
Power/Cabinet ≤ 300
modules first.
kW
kW
185
240
95
120
Secured Installation
170 kW < Output
210 kW < Output
Power/Cabinet ≤ 210
Power/Cabinet ≤ 250
kW
kW
185
240
95
120
Unit: mm
Space Planning
Unit: mm
Against a Wall
After installing expansion bolts, reinstall the tray.
M12 bolt
Spring
washer
Flat washer
Concrete
Expansion
floor
sleeve
Expansion
nut
Not Against a Wall
Rubber
plug
Rubber
plug
1
Issue: 04
Date: 2022-10-15
Non-Secured Installation
Combining Cabinets
Adjust the anchor bolts until the castors hang in
the air, ensure that the anchor bolts fully
support the cabinet, and use a level instrument
to check that the cabinet is level.
If the cabinet is installed against a wall, install only the front connecting plates.
03
Installing a Ground Cable
1. Remove the PDU cover and the ground cable gland nut and sealing plugs.
2. Install a ground cable.
Site ground bar
Remove certain
sealing plugs
based on the
cable size.
Supported Cable Diameter
Gland
Sealing Plug to Be
(Including the Insulation Layer,
Model
Removed
Unit: mm)
Innermost layer (white)
10–16
M40 (10–32)
Innermost layer (white),
16–22
second-to-last layer (red)
The single-core 90°C-resistant flexible copper cable is used as an example in the table to illustrate which
sealing plugs need to be removed. The sealing plugs to be removed depend on the actual cable
diameter (including the insulation layer). Remove sealing plugs only when necessary. Otherwise, the
sealing performance will be affected.
3. Reinstall the sealing plugs. (The sealing plugs must be completely inserted into the gland
to facilitate the reinstallation of the gland nut.)
4. Reinstall the gland nut with a torque of 8 N· m.
Recommended Cable
Size (Unit: mm
2
)
-
70, 95, 120

Advertisement

loading

Summary of Contents for Huawei SmartLi-512V-162Ah-F

  • Page 1 Do not transport a Model Weight Configuration Type cabinet with SmartLi-512V-162Ah-F With an LCD (master cabinet) < 1100 kg battery modules SmartLi-512V-162Ah-S Without an LCD (slave cabinet) If the cabinet is installed against a wall, install only the front connecting plates.
  • Page 2: Preparing Power Cables

    SmartLi 3.0 Quick Guide (Short-Term Backup Power) Installing Output Power Cables Preparing Power Cables Installing Output Power Cables 3. Reinstall the sealing plugs. (The sealing plugs must be completely inserted into the gland to facilitate the reinstallation of the gland nut.) 1.
  • Page 3 SmartLi 3.0 Quick Guide (Short-Term Backup Power) Installing Battery Modules 1. Pull out the BCU. 3. Check the insulation performance of the battery 4. Install battery communications cables. 5. Install battery copper bars and power cables. (7+7 8. Attach PP sheets to the notches of the battery modules and secure the modules.
  • Page 4 SmartLi 3.0 Quick Guide (Short-Term Backup Power) Verifying the Installation Power-On Item Acceptance Criteria • Turn on the ready switch on the BCU. Cabinet The cabinet is securely installed and does not tilt due to vibration. • Ensure that the UPS runs stably in normal mode and the rectifier shown in the energy flow diagram is started. installation Neat arrangement The adjacent cabinets are neatly arranged and secured with connecting kits.
  • Page 5 5. After the green indicator of the BCU blinks at super short intervals and the red indicator is • LCD Preset WebUI Preset The preceding parameters are described for Huawei UPS5000 series. For third-party UPSs, System User steady on, switch on the battery circuit breaker on the battery cabinet. Password Password set the parameters by referring to the preceding description.
  • Page 6 The preceding procedure applies to the single-cabinet scenario. For the multi-cabinet scenario, see SmartLi 3.0 User Manual (Short-Term Backup Power) Copyright © Huawei Digital Power Technologies Co., Ltd. 2022. All rights reserved.

This manual is also suitable for:

Smartli-512v-162ah-s