Download Print this page

ABB J2013001 Quick Start Manual page 5

1u stackable distribution shelf - 19 in rack mount

Advertisement

QUICK START GUIDE
Step 7 - Connect Bullet Circuit Breaker Loads - skip if not present
Step 8 - Connect Snapak Circuit Breaker Loads - skip if not present
1.
Verify that breaker is OFF or not installed.
2.
Remove detachable terminal block
3.
Insert load and load return wires Strip 0.4 in (10 mm)
4.
Torque to 6.5 in-lb (0.75 Nm).
5.
Pull wires to verify.
6.
Insert detachable terminal block fully.
Step 9 - Connect GMT Style Fuse Loads - skip if not present
skip if not present Connections for Load GMT Fuses to GMT terminal blocks identified as "-48VDC" and "RTNS" on
labels above each row of terminals blocks.
Wire Size: 24-12AWG
Strip Length: 0.35" (9mm)
1.
Verify that fuse is not installed.
2.
Strip wires
3.
Insert wires into terminal blocks labeled -48VDC and associated RTNS.
4.
Tighten screw - 4 in-lb (0.45 Nm).
5.
Pull wire to verify.
Page 5
© 2021 ABB. All rights reserved.
Cover Screws
-48V Lug Landings
-Return Lug Landings
3-Circuit Blocks - Load Only
Bullet Breaker Connections
(ID Label and Breaker landing covers not shown)
8 AWG (6 mm2) max.
Detachable Terminal Block
Snapak Breaker Connections
Screw
(continued)
Load Return
-48V Load

Advertisement

loading