Huawei PDU8000 Quick Manual page 34

Dc combiner cabinet
Hide thumbs Also See for PDU8000:
Table of Contents

Advertisement

PDU8000 DC Combiner Cabinet
Quick Guide
No.
5
Table 7-3 Checking cable installation
No.
1
2
3
4
5
6
Issue 02 (2022-08-10)
Expected Result
All circuit breakers are OFF.
Expected Result
All bolts and screws are firmly tightened, especially
on electrical connections. Flat and spring washers
are used with each bolt, and spring washers are
placed on the top of flat washers.
Cable installation meets the cable routing
requirements.
Cables are routed in a way convenient for future
maintenance and expansion.
There is no unnecessary adhesive tape or cable tie
on cables.
Exposed parts near the wiring terminals and lugs
are wrapped with insulation tape or heat shrinking
tubing.
Routing of power cables and monitoring cables
meets the requirements for routing electric and ELV
cables and complies with the cable routing plan.
Copyright © Huawei Digital Power Technologies Co., Ltd.
7 Verifying the Installation
Check Result
□ Passed □
Failed
Check Result
□ Passed □
Failed
□ Passed □
Failed
□ Passed □
Failed
□ Passed □
Failed
□ Passed □
Failed
□ Passed □
Failed
29