Beko BEKOKAT CC-720 Installation And Operation Manual page 62

Catalytic converter
Table of Contents

Advertisement

Installation and Operation Manual BEKOKAT
10th
After a heating phase of about 6 hours, the target temperature of + 150 °C is set in the
catalytic bed. The white indicator goes out and the green "Reactor ON" (H1) indicator
comes on.
The compressed air supply is automatically opened via the solenoid valve Y1.
Below a stable operating point is reached where the actual temperature can fluctuate
by the set target value of about +/- 5 °C. For this purpose, the changing operating
conditions due to load and idle time of the compressor are responsible.
11th
No additional adjustments are required to be implemented after successful
commissioning.
®
BEKOKAT
is now ready for use. The operation is fully automatic.
Should unforeseen malfunctions occur during ongoing operation, then please notify
your responsible service technician.
62 / 88
®
V01 /11-038