QUICK START GUIDE
Step 5 - Install Breakers and Fuses
Install breakers into positions as specified in Site Engineering
Instructions.
Use only breakers specified in the Slimline Power System
Brochure - 30A max.
1.
Remove Cover (2 thumb screws).
2.
Verify that each Breaker is OFF.
3.
Insert each Breaker fully into its position
— oriented with ON position at top.
4.
Remove cover knockouts for installed positions.
5.
Replace Cover (2 thumb screws).
6.
Turn each Breaker ON.
7.
Install each GMT style fuse fully into its position – oriented as shown – 15A max.
Step 6 - Set Jumpers
Quick Start Guide.
Step 7
Install Controller per Galaxy Pulsar Edge Controller Quick Start Guide
-
Step 8 - Install Signal and Communications Cables
1.
J1-2Alarms and Inputs - Connect to office alarms and signals.
See Information: Alarm Connections for Details
2.
J5 LAN - Connect to Ethernet network.
Step 9- Install Rectifiers
Firmly push the rectifier into the rectifier slot.
Tighten the thumb screw until the rectifier is seated.
NOTE: When installing a rectifier in a powered system
the RUN LED on the rectifier will blink until
communication with the controller is established.
Step 10 - Initial Start Up
Verify that all AC, DC and Alarm connections are complete and secure. Turn on AC input breakers. If there are no
alarms, make required adjustments to the default settings on the controller for this installation.
Page 3
© 2023 ABB. All rights reserved.
LAN Port and Relay per Galaxy Pulsar Edge Controller
-
SPS -48V Shelf_QSG
Rev. 2.0

Advertisement

loading

This manual is also suitable for:

Sps-48v