The following is the sequence of steps for closing and opening the circuit-breaker:
1.
Check that the circuit-breaker is open (open / closed indicator "O - OPEN"), and check that the
springs are discharged (spring signalling device "white - DISCHARGED SPRING") as indicated in
Figure 18.
2.
Charging the springs - Pull the lever [A] downwards several times until the springs charged
signalling device [B] is "yellow - CHARGED SPRING" as indicated in Figure 19.
Figure 18
3.
Check that the circuit-breaker is open (open/closed signalling device "O - OPEN"), and check that
the springs are charged (springs signalling device "yellow - CHARGED SPRING") as indicated in
Figure 20.
4.
Closing - Press the closing pushbutton "I - Push ON" as indicated in Figure 21.
Figure 20
5.
Check that the circuit-breaker is closed (open/closed indicator "I - CLOSED"), and check that the
springs are discharged (spring signalling device "white - DISCHARGED SPRING" as indicated in
Figure 22.
6.
Opening - Press the opening pushbutton "O - Push OFF" as indicated in Figure 23.
Figure 22
A B
Figure 19
Figure 21
Figure 23
Continued on the next page
Management operations
ABB | SACE Emax 2
3 - Description

Advertisement

Table of Contents
loading

Table of Contents