General checks Before putting it into service for the first time or after a prolonged period of inactivity, some checks must
42 | © 2022 ABB | 1SDH000999R0002 - ECN000297030
be carried out on the circuit-beaker and the environment in which it is installed:
Points to be che-
Checks
cked
1. Sufficient change of air to avoid overtemperatures
2. Clean location, free of all installation refuse (e.g.: cables, tools, metal
splinters)
Switchgear
3. Circuit-breaker mounted correctly (tightening torques, clearances
respected)
4. The installation environmental conditions must be consistent with the
"Environmental conditions" specifications on page20
1. Power connections tightened to the terminals of the circuit-breaker
2. Cables and busbars with adequate cross-section
Connections
3. Correct ground connections
4. Maximum distances of separators respected
Perform some opening and closing operations (See chapter "Description of
the product - circuit-breaker opening/closing operations on page15). The
spring loading lever must move with regularly
Operations
WARNING! in the presence of an undervoltage coil the circuit-breaker
can be closed only after the trip unit is energized
Connect the protection device Ekip TT to the trip unit and verify that there
Trip unit alarm
are no alarms present
State of the circuit-
With Ekip Dip, the circuit-breaker state must not be in error (see table on
breaker with Ekip
page38). Perform a circuit-breaker closing/opening operation and make sure
Dip
that there are no alarms (see table on page38)
State of the circuit-
With Ekip Touch, the circuit-breaker state must be read correctly (see table
breaker with Ekip
on page38). Perform a circuit-breaker closing/opening operation and make
Touch
sure that change of state is read correctly
With circuit-breaker closed and in conditions of rest (without circulating
Trip Test
currents), carry out a Trip test, and verify the opening of the circuit-breaker
Ekip Dip
Check and modify the protection dip switches, presence of external neutral
parameters
and frequency to suit your installation requirements
Connect the Ekip TT device. Check and make the necessary changes to:
Ekip Touch
protection parameters, circuit-breaker configuration, frequency, PIN, date
parameters
and language
NOTE: for security reasons, ABB strongly advises you to change the PIN right from the first
access and to keep it with care.
ABB | SACE Emax 2
Putting into service and maintenance
1 - Putting into service