Test sequence
– In particular, make sure that the 12 V DC fuse (+F03-FC23) is switched on and that the
7. Install the roof, the baseboards and the panel in the top area of the charging station.
8. Close the doors.
9. Power on the charging station via the upstream switching device.
10. After power on and successful initialization of the charging station, the AC port is ready for
charging. Now conduct the measurements of the residual current circuit breaker for AC
charging. Carry out the triggering measurement last.
11. Shut down the charging station properly via the HMI. To do this, open the door and press
the "Shut down" button. De-energize the charging station via the upstream switching device
as soon as the LED strips on the housing are switched off.
12. Reset the residual current circuit breaker. Close the device door.
Commissioning is complete. The charging station can be powered on for operation by
customers via the upstream switching element.