Press ENTER. When the cursor becomes a static
underline, press either the UP OR DOWN arrow
key once and the screen should show "HTS #1
Enabled".
Press ENTER to save the setting.
To confirm that the controller is communicating
properly with the HTS transfer switch, use the
ARROW keys to scroll to the bottom of the screen
and select the "go back" arrow (
Press ENTER. If the top line of the display shows
"HTS #1 Enabled", the controller is properly
configured and you can return to the main menu
display by pressing MENU.
If the display shows "HTS #1 Disabled", go back to
page (4 - 4) to enable the switch, then check again.

OPERATIONAL CHECkS

Make sure all breakers in the main
distribution panel are open so that loads
cannot be accidentally transferred to the
generator until you are ready to do so.
To conduct the necessary operational
checks you will have to work inside a live
transfer switch. Refer to NFPA 70E for the
required safety equipment.
With utility power present and the
generator in the OFF position, select
AUTO in the transfer switch.