About this section

This section describes the basic operation procedures you can carry out after the IEC103
OPC Server has been configured.
After this, you can, for example, monitor and control the condition of connections in an
IEC103 network. This is done by using the Online diagnostics function in SAB600.

Activating COM600 with new configurations

For information about activating COM600 with new configuration, see COM600 User's
Manual.

IEC103 OPC Server diagnostics

To view the IEC103 OPC Server diagnostics, right-click the IEC103 OPC Server object
and select Online diagnostics , see Figure 4.3-1 .
Figure 4.3-1 IEC103 OPC Server Online diagnostics
You have the following alternatives:
to view version information
to reset the IEC103 OPC Server
to view the event log file , see Figure 4.3-2
to clear the log file