Test Method - NEC NEAX2400 ICS Installation Notes

Isdn pri
Hide thumbs Also See for NEAX2400 ICS:
Table of Contents

Advertisement

NEAX2400 ICS ISDN PRI Installation Notes
6.

TEST METHOD

The following test method will allow you to verify the proper operation of the ISDN PRI in the
PBX without a physical connection to the network.
In order to accomplish a ISDN PRI internal test, two 24PRTs are necessary - one PRT configured
as the user side (normal operation) and the second PRT configured as the network side. The two
PRTs should be connected together.
To configure the 24PRT as a network side (for test purposes only), set the ARTD command CDN
64 = 1 and SW4 element 2 = OFF = network side.
You should be able to place calls from Station A via ISDN to Station B.
Figure 7 shows the connection of two 24PRTs for test purposes.
STATION A
STATION B
ISMC
ETI-152A
24PRT
24PRT
Figure 7 Connection of 24PRTs for Test Purpose
Command is used for monitoring the ISDN PRI D-Channel messages. By
entering the specific DCH, LEN, and specific type of messages to be displayed,
you can monitor Layer 2 or Layer 3 messages. Knowledge of ISDN Protocol is
required for interpreting these messages.
ISMC Command requires the use of software E6.2 (or higher) and MAT
Note:
Command B10.10 (or higher).
MDF
RA
RB
TA
TB
RA1
RB1
TA1
TB1
Page 28