Installing/Routing Cables
10.3

Installing Cabinet and Subrack Ground Cables

Installing A63B Cabinet Ground Cables
Installing A66B Cabinet Ground Cables
NOTE
There are two groups of ground screws on the top of the A66B cabinet, and only one group of
ground screws is required. You are advised to preferentially select the group with a ground label.
To the ground bar
in the equipment
room
To the ground bar
in the equipment
room
57
M8
12.24±1.22 N· m
M8
12.24±1.22N.M