System Commissioning; Verification Before Power-On - Huawei LUNA2000 Series User Manual

Hide thumbs Also See for LUNA2000 Series:
Table of Contents

Advertisement

LUNA2000-(5-30)-S0
User Manual

6.1 Verification Before Power-On

6.2 System Power-On
6.3 Battery Commissioning
6.1 Verification Before Power-On
Table 6-1 Check items and acceptance criteria
No.
1
2
3
4
5
6
7
8
Issue 01 (2020-09-18)
6
Check Item
Battery installation
Cables routing
Cable tie
Grounding
Switch
Cable connection
Unused terminal and port
Installation environment
Copyright © Huawei Technologies Co., Ltd.

System Commissioning

Acceptance Criteria
The installation is correct and reliable.
Cables are routed properly as required by the
customer.
Cable ties are evenly distributed and no burr
exists.
The PE cable is connected correctly,
securely, and reliably.
The DC switch and all switches connected to
the battery are OFF.
The AC output power cable, DC input power
cable, battery cable, and signal cable are
connected correctly, securely, and reliably.
Unused terminals and ports are locked by
watertight caps.
The installation space is proper, and the
installation environment is clean and tidy.
6 System Commissioning