8.2 Commissioning work

Illustration
X3
X2
X2
46 | 76
X3
Original installation and operation manual
Description / explanation
1. Connect the voltage supply.
0 The BEKOMAT
carries out the power-on self-test.
®
2. Slowly pressurise the system (e.g. by slowly opening
the recommended shut-off valve [X3] in the
condensate inlet line [X2]).
3. Carry out a functional test (see "10.3.2 Functional test"
on Page 57).