3.3.2 Installation Process

Figure 3-5 Installation process
3.3.3 Installation and Cable Connection (400K/500K/600K/
800K/1200K)
Step 1 Connect the ground cable of the ESD wrist strap, and put on the ESD wrist strap
and ESD gloves.
Step 2 Install an optional BSC card on any UPS in the slave system.
Figure 3-6 Installing an optional BSC card
Step 3 Install cables between an optional BSC card and ECMs.