ABB RELION 670 Series Commissioning Manual

Line differential protection version 2.1 iec
Hide thumbs Also See for RELION 670 Series:
Table of Contents

Advertisement

Quick Links

R E L I O N ® 670 SERIES
Line differential protection RED670
Version 2.1 IEC
Commissioning manual

Advertisement

Table of Contents
loading

Summary of Contents for ABB RELION 670 Series

  • Page 1 — R E L I O N ® 670 SERIES Line differential protection RED670 Version 2.1 IEC Commissioning manual...
  • Page 3 Document ID: 1MRK 505 345-UEN Issued: March 2019 Revision: B Product version: 2.1 © Copyright 2016 ABB. All rights reserved...
  • Page 4 Copyright This document and parts thereof must not be reproduced or copied without written permission from ABB, and the contents thereof must not be imparted to a third party, nor used for any unauthorized purpose. The software and hardware described in this document is furnished under a license and may be used or disclosed only in accordance with the terms of such license.
  • Page 5 This document has been carefully checked by ABB but deviations cannot be completely ruled out. In case any errors are detected, the reader is kindly requested to notify the manufacturer.
  • Page 6 (Low-voltage directive 2006/95/EC). This conformity is the result of tests conducted by ABB in accordance with the product standard EN 60255-26 for the EMC directive, and with the product standards EN 60255-1 and EN 60255-27 for the low voltage directive. The...
  • Page 7: Table Of Contents

    Table of contents Table of contents Section 1 Introduction....................... 11 This manual............................11 Intended audience..........................11 Product documentation........................12 1.3.1 Product documentation set.......................12 1.3.2 Document revision history......................13 1.3.3 Related documents........................13 Document symbols and conventions...................14 1.4.1 Symbols............................14 1.4.2 Document conventions.......................15 IEC61850 edition 1 / edition 2 mapping..................15 Section 2 Safety information...................
  • Page 8 Table of contents Section 5 Configuring the IED and changing settings..........51 Overview.............................51 Configuring analog CT inputs......................51 Reconfiguring the IED........................52 Section 6 Establishing connection and verifying the SPA/IEC communication..53 Entering settings..........................53 6.1.1 Entering SPA settings.........................53 6.1.2 Entering IEC settings........................53 Verifying the communication......................54 6.2.1 Verifying SPA communication....................
  • Page 9 Table of contents 9.8.4.2 Undo forcing by using LHMI....................74 9.8.4.3 Undo forcing by using PCM600.....................74 Section 10 Testing functionality by secondary injection..........75 10.1 Testing disturbance report......................75 10.1.1 Introduction..........................75 10.1.2 Disturbance report settings......................75 10.1.3 Disturbance recorder (DR)......................75 10.1.4 Event recorder (ER) and Event list (EL)...................
  • Page 10 Table of contents 10.4.8 High Speed distance for series compensated line zones, quadrilateral and mho characteristic ZMFCPDIS ......................101 10.4.8.1 Measuring the operating limit of set values..............104 10.4.8.2 Measuring the operating time of distance protection zones........104 10.4.8.3 Completing the test.......................105 10.4.9 Power swing detection ZMRPSB ...................
  • Page 11 Table of contents 10.5.4.2 Four step non-directional earth fault protection.............132 10.5.4.3 Completing the test....................... 133 10.5.5 Four step negative sequence overcurrent protection NS4PTOC ........133 10.5.5.1 Completing the test.......................134 10.5.6 Sensitive directional residual overcurrent and power protection SDEPSDE ....134 10.5.6.1 Measuring the operate and time limit for set values............134 10.5.6.2 Completing the test.......................138 10.5.7...
  • Page 12 Table of contents 10.6.2.3 Completing the test.......................152 10.6.3 Two step residual overvoltage protection ROV2PTOV ............. 152 10.6.3.1 Verifying the settings......................152 10.6.3.2 Completing the test.......................153 10.6.4 Overexcitation protection OEXPVPH ..................153 10.6.4.1 Verifying the settings......................153 10.6.4.2 Completing the test.......................154 10.6.5 Voltage differential protection VDCPTOV ................
  • Page 13 Table of contents 10.9.2.5 Checking the operation of the du/dt and di/dt based function .........168 10.9.2.6 Completing the test.......................169 10.9.3 Fuse failure supervision VDSPVC................... 169 10.9.3.1 Completing the test.......................170 10.10 Control..............................170 10.10.1 Synchrocheck, energizing check, and synchronizing SESRSYN........170 10.10.1.1 Testing the synchronizing function..................171 10.10.1.2 Testing the synchrocheck check..................172 10.10.1.3...
  • Page 14 Table of contents 10.11.6.1 Testing the current reversal logic..................190 10.11.6.2 Testing the weak-end infeed logic..................190 10.11.6.3 Completing the test.......................192 10.11.7 Direct transfer trip logic......................192 10.11.7.1 Low active power and power factor local criteria LAPPGAPC........192 10.11.7.2 Compensated over- and undervoltage protection COUVGAPC........193 10.11.7.3 Sudden change in current variation SCCVPTOC..............
  • Page 15 Table of contents 10.17 Basic IED functions........................210 10.17.1 Parameter setting group handling SETGRPS...............210 10.17.1.1 Verifying the settings......................210 10.17.1.2 Completing the test.......................210 10.18 Exit test mode..........................210 Section 11 Checking the directionality................211 11.1 Overview............................211 11.2 Testing the directionality of the distance protection.............211 Section 12 Commissioning and maintenance of the fault clearing system....
  • Page 17: Introduction

    1MRK 505 345-UEN B Section 1 Introduction Section 1 Introduction This manual GUID-AB423A30-13C2-46AF-B7FE-A73BB425EB5F v19 The commissioning manual contains instructions on how to commission the IED. The manual can also be used by system engineers and maintenance personnel for assistance during the testing phase.
  • Page 18: Product Documentation

    Section 1 1MRK 505 345-UEN B Introduction Product documentation 1.3.1 Product documentation set GUID-3AA69EA6-F1D8-47C6-A8E6-562F29C67172 v15 Engineering manual Installation manual Commissioning manual Operation manual Application manual Technical manual Communication protocol manual Cyber security deployment guideline IEC07000220-4-en.vsd IEC07000220 V4 EN-US Figure 1: The intended use of manuals throughout the product lifecycle The engineering manual contains instructions on how to engineer the IEDs using the various tools available within the PCM600 software.
  • Page 19: Document Revision History

    1MRK 505 345-UEN B Section 1 Introduction The application manual contains application descriptions and setting guidelines sorted per function. The manual can be used to find out when and for what purpose a typical protection function can be used. The manual can also provide assistance for calculating settings. The technical manual contains operation principle descriptions, and lists function blocks, logic diagrams, input and output signals, setting parameters and technical data, sorted per function.
  • Page 20: Document Symbols And Conventions

    Section 1 1MRK 505 345-UEN B Introduction 670 series manuals Document numbers Cyber security deployment guideline 1MRK 511 356-UEN Connection and Installation components 1MRK 513 003-BEN Test system, COMBITEST 1MRK 512 001-BEN Document symbols and conventions 1.4.1 Symbols GUID-2945B229-DAB0-4F15-8A0E-B9CF0C2C7B15 v12 The electrical warning icon indicates the presence of a hazard which could result in electrical shock.
  • Page 21: Document Conventions

    1MRK 505 345-UEN B Section 1 Introduction 1.4.2 Document conventions GUID-96DFAB1A-98FE-4B26-8E90-F7CEB14B1AB6 v8 • Abbreviations and acronyms in this manual are spelled out in the glossary. The glossary also contains definitions of important terms. • Push button navigation in the LHMI menu structure is presented by using the push button icons.
  • Page 22 Section 1 1MRK 505 345-UEN B Introduction Function block name Edition 1 logical nodes Edition 2 logical nodes BUSPTRC_B8 BUSPTRC BUSPTRC BUSPTRC_B9 BUSPTRC BUSPTRC BUSPTRC_B10 BUSPTRC BUSPTRC BUSPTRC_B11 BUSPTRC BUSPTRC BUSPTRC_B12 BUSPTRC BUSPTRC BUSPTRC_B13 BUSPTRC BUSPTRC BUSPTRC_B14 BUSPTRC BUSPTRC BUSPTRC_B15 BUSPTRC BUSPTRC BUSPTRC_B16...
  • Page 23 1MRK 505 345-UEN B Section 1 Introduction Function block name Edition 1 logical nodes Edition 2 logical nodes CBPGAPC CBPLLN0 CBPMMXU CBPMMXU CBPPTRC CBPPTRC HOLPTOV HOLPTOV HPH1PTOV HPH1PTOV PH3PTOC PH3PTUC PH3PTUC PH3PTOC RP3PDOP RP3PDOP CCPDSC CCRPLD CCPDSC CCRBRF CCRBRF CCRBRF CCRWRBRF CCRWRBRF CCRWRBRF...
  • Page 24 Section 1 1MRK 505 345-UEN B Introduction Function block name Edition 1 logical nodes Edition 2 logical nodes GENPDIF GENPDIF GENGAPC GENPDIF GENPHAR GENPTRC GOOSEBINRCV BINGREC GOOSEDPRCV DPGREC GOOSEINTLKRCV INTGREC GOOSEINTRCV INTSGREC GOOSEMVRCV MVGREC GOOSESPRCV BINSGREC GOOSEVCTRRCV VCTRGREC GOPPDOP GOPPDOP GOPPDOP PH1PTRC GRPTTR...
  • Page 25 1MRK 505 345-UEN B Section 1 Introduction Function block name Edition 1 logical nodes Edition 2 logical nodes LPHD LPHD LPTTR LPTTR LPTTR LT3CPDIF LT3CPDIF LT3CGAPC LT3CPDIF LT3CPHAR LT3CPTRC LT6CPDIF LT6CPDIF LT6CGAPC LT6CPDIF LT6CPHAR LT6CPTRC MVGAPC MVGGIO MVGAPC NS2PTOC NS2LLN0 NS2PTOC NS2PTOC NS2PTRC...
  • Page 26 Section 1 1MRK 505 345-UEN B Introduction Function block name Edition 1 logical nodes Edition 2 logical nodes SAPTOF SAPTOF SAPTOF SAPTUF SAPTUF SAPTUF SCCVPTOC SCCVPTOC SCCVPTOC SCILO SCILO SCILO SCSWI SCSWI SCSWI SDEPSDE SDEPSDE SDEPSDE SDEPTOC SDEPTOV SDEPTRC SESRSYN RSY1LLN0 AUT1RSYN AUT1RSYN...
  • Page 27 1MRK 505 345-UEN B Section 1 Introduction Function block name Edition 1 logical nodes Edition 2 logical nodes U2RWPTUV GEN2LLN0 PH1PTRC PH1PTRC U2RWPTUV U2RWPTUV UV2PTUV GEN2LLN0 PH1PTRC PH1PTRC UV2PTUV UV2PTUV VDCPTOV VDCPTOV VDCPTOV VDSPVC VDRFUF VDSPVC VMMXU VMMXU VMMXU VMSQI VMSQI VMSQI VNMMXU...
  • Page 29: Safety Information

    1MRK 505 345-UEN B Section 2 Safety information Section 2 Safety information Symbols on the product GUID-E48F2EC3-6AB8-4ECF-A77E-F16CE45CA5FD v2 All warnings must be observed. Read the entire manual before doing installation or any maintenance work on the product. All warnings must be observed. Class 1 Laser product.
  • Page 30: Caution Signs

    Section 2 1MRK 505 345-UEN B Safety information M2370-2 v1 Never connect or disconnect a wire and/or a connector to or from a IED during normal operation. Hazardous voltages and currents are present that may be lethal. Operation may be disrupted and IED and measuring circuitry may be damaged.
  • Page 31: Note Signs

    1MRK 505 345-UEN B Section 2 Safety information M2695-2 v2 Always transport PCBs (modules) using certified conductive bags. M2696-2 v1 Do not connect live wires to the IED. Internal circuitry may be damaged M2697-2 v2 Always use a conductive wrist strap connected to protective earth when replacing modules.
  • Page 33: Available Functions

    1MRK 505 345-UEN B Section 3 Available functions Section 3 Available functions Main protection functions GUID-66BAAD98-851D-4AAC-B386-B38B57718BD2 v12.1.1 Table 2: Example of quantities = number of basic instances = option quantities 3-A03 = optional function included in packages A03 (refer to ordering details) IEC 61850 ANSI Function description...
  • Page 34 Section 3 1MRK 505 345-UEN B Available functions IEC 61850 ANSI Function description Line Differential RED670 (Customized) ZMHPDIS Fullscheme distance 4-B17 4-B17 4-B17 4-B17 protection, mho characteristic ZMMPDIS, Fullscheme distance 4-B17 4-B17 4-B17 4-B17 ZMMAPDIS protection, quadrilateral for earth faults ZDMRDIR Directional impedance 1-B17...
  • Page 35: Back-Up Protection Functions

    1MRK 505 345-UEN B Section 3 Available functions Back-up protection functions GUID-A8D0852F-807F-4442-8730-E44808E194F0 v10 IEC 61850 ANSI Function description Line Differential RED670 (Customized) Current protection PHPIOC Instantaneous phase overcurrent protection OC4PTOC Four step phase 51_67 overcurrent protection EFPIOC Instantaneous 1-C24 1-C24 1-C24 1-C24 residual overcurrent...
  • Page 36 Section 3 1MRK 505 345-UEN B Available functions IEC 61850 ANSI Function description Line Differential RED670 (Customized) UV2PTUV Two step undervoltage protection OV2PTOV Two step overvoltage protection ROV2PTOV Two step residual overvoltage protection OEXPVPH Overexcitation 1-D03 1-D03 1-D03 1-D03 protection VDCPTOV Voltage differential protection...
  • Page 37: Control And Monitoring Functions

    1MRK 505 345-UEN B Section 3 Available functions Control and monitoring functions GUID-E3777F16-0B76-4157-A3BF-0B6B978863DE v12 IEC 61850 ANSI Function description Line Differential RED670 Control SESRSYN Synchrocheck, energizing check and synchronizing SMBRREC Autorecloser 1-H04 2-H05 1-H04 2-H05 APC10 Apparatus control for 1-H27 1-H27 single bay, max 10 apparatuses (1CB) incl.
  • Page 38 Section 3 1MRK 505 345-UEN B Available functions IEC 61850 ANSI Function description Line Differential RED670 I103USRCMD Function commands user defined for IEC 60870-5-103 Secondary system supervision CCSSPVC Current circuit supervision FUFSPVC Fuse failure supervision VDSPVC Fuse failure supervision 1-G03 1-G03 1-G03 1-G03...
  • Page 39 1MRK 505 345-UEN B Section 3 Available functions IEC 61850 ANSI Function description Line Differential RED670 ITBGAPC Integer to Boolean 16 conversion with Logic Node representation TEIGAPC Elapsed time integrator with limit transgression and overflow supervision INTCOMP Comparator for integer inputs REALCOMP Comparator for real...
  • Page 40 Section 3 1MRK 505 345-UEN B Available functions IEC 61850 ANSI Function description Line Differential RED670 I103EF Function status earth- fault for IEC 60870-5-103 I103FLTPROT Function status fault protection for IEC 60870-5-103 I103IED IED status for IEC 60870-5-103 I103SUPERV Supervison status for IEC 60870-5-103 I103USRDEF Status for user defined...
  • Page 41: Communication

    1MRK 505 345-UEN B Section 3 Available functions Configurable logic blocks Q/T Total number of instances ORQT PULSETIMERQT RSMEMORYQT SRMEMORYQT TIMERSETQT XORQT Table 5: Total number of instances for extended logic package Extended configurable logic block Total number of instances GATE PULSETIMER SLGAPC...
  • Page 42 Section 3 1MRK 505 345-UEN B Available functions IEC 61850 ANSI Function description Line Differential RED670 (Customized) DNPGENTCP DNP3.0 communication general TCP protocol CHSERRS485 DNP3.0 for EIA-485 communication protocol CH1TCP, CH2TCP, DNP3.0 for TCP/IP CH3TCP, CH4TCP communication protocol CHSEROPT DNP3.0 for TCP/IP and EIA-485 communication protocol...
  • Page 43 1MRK 505 345-UEN B Section 3 Available functions IEC 61850 ANSI Function description Line Differential RED670 (Customized) OPTICAL103 IEC 60870-5-103 Optical serial communication RS485103 IEC 60870-5-103 serial communication for RS485 AGSAL Generic security application component LD0LLN0 IEC 61850 LD0 LLN0 SYSLLN0 IEC 61850 SYS LLN0 LPHD...
  • Page 44: Basic Ied Functions

    Section 3 1MRK 505 345-UEN B Available functions IEC 61850 ANSI Function description Line Differential RED670 (Customized) ZC1PPSCH Phase segregated 1-B05 1-B05 scheme communication logic for distance protection ZCRWPSCH Current reversal and 1-B11 1-B11 1-B11 1-B11 weak-end infeed logic 1-B16 1-B16 1-B16 1-B16...
  • Page 45 1MRK 505 345-UEN B Section 3 Available functions IEC 61850 or function Description name SMBI Signal matrix for binary inputs SMBO Signal matrix for binary outputs SMMI Signal matrix for mA inputs SMAI1 - SMAI12 Signal matrix for analog inputs 3PHSUM Summation block 3 phase ATHSTAT...
  • Page 47: Starting Up

    1MRK 505 345-UEN B Section 4 Starting up Section 4 Starting up Factory and site acceptance testing GUID-38C2B5FA-9210-4D85-BA21-39CE98A1A84A v2 Testing the proper IED operation is carried out at different occasions, for example: • Acceptance testing • Commissioning testing • Maintenance testing This manual describes the workflow and the steps to carry out the commissioning testing.
  • Page 48: Checking The Power Supply

    Section 4 1MRK 505 345-UEN B Starting up Checking the power supply M11725-2 v6 Do not insert anything else to the female connector but the corresponding male connector. Inserting anything else (such as a measurement probe) may damage the female connector and prevent a proper electrical contact between the printed circuit board and the external wiring connected to the screw terminal block.
  • Page 49: Setting Up Communication Between Pcm600 And The Ied

    1MRK 505 345-UEN B Section 4 Starting up t (s) xx04000310-1-en.vsd IEC04000310 V2 EN-US Figure 2: Typical IED start-up sequence 1 IED energized. Green LED instantly starts flashing 2 LCD lights up and "IED startup" is displayed 3 The main menu is displayed. A steady green light indicates a successful startup. If the upper row in the window indicates ‘Fail’...
  • Page 50 Section 4 1MRK 505 345-UEN B Starting up • The default IP address for the IED front port is 10.1.150.3 and the corresponding subnetwork mask is 255.255.255.0, which can be set via the local HMI path Main menu/ Configuration/Communication/Ethernet configuration/FRONT:1. Setting up the PC or workstation for point-to-point access to IEDs front port An ethernet cable (max 2 m length) with RJ-45 connectors is needed to connect two physical...
  • Page 51 1MRK 505 345-UEN B Section 4 Starting up IEC13000057-1-en.vsd IEC13000057 V1 EN-US Figure 4: Select: Search programs and files Type View network connections and click on the View network connections icon. Commissioning manual...
  • Page 52 Section 4 1MRK 505 345-UEN B Starting up IEC13000058-1-en.vsd IEC13000058 V1 EN-US Figure 5: Click View network connections Right-click and select Properties. IEC13000059-1-en.vsd IEC13000059 V1 EN-US Figure 6: Right-click Local Area Connection and select Properties Select the TCP/IPv4 protocol from the list of configured components using this connection and click Properties.
  • Page 53 1MRK 505 345-UEN B Section 4 Starting up IEC13000060-1-en.vsd IEC13000060 V1 EN-US Figure 7: Select the TCP/IPv4 protocol and open Properties IP address and Subnet mask if the front Select Use the following IP address and define IP address is not set to be obtained automatically by the IED, see port is used and if the Figure 8.
  • Page 54: Writing An Application Configuration To The Ied

    Section 4 1MRK 505 345-UEN B Starting up The PC and IED must belong to the same subnetwork for this set-up to work. Setting up the PC to access the IED via a network The same method is used as for connecting to the front port. The PC and IED must belong to the same subnetwork for this set-up to work.
  • Page 55: Checking Vt Circuits

    1MRK 505 345-UEN B Section 4 Starting up Both the primary and the secondary sides must be disconnected from the line and the IED when plotting the excitation characteristics. If the CT secondary circuit earth connection is removed without the current transformer primary being de-energized, dangerous voltages may result in the secondary CT circuits.
  • Page 56: Checking The Binary I/O Circuits

    Section 4 1MRK 505 345-UEN B Starting up Verify that the contact sockets have been crimped correctly and that they are fully inserted by tugging on the wires. Never do this with current circuits in service. Current circuit Verify that the contacts are of current circuit type. Verify that the short circuit jumpers are located in the correct slots.
  • Page 57: Configuring The Ied And Changing Settings

    1MRK 505 345-UEN B Section 5 Configuring the IED and changing settings Section 5 Configuring the IED and changing settings Overview M11730-2 v6 The customer specific values for each setting parameter and a configuration file have to be available before the IED can be set and configured, if the IED is not delivered with a configuration.
  • Page 58: Reconfiguring The Ied

    Section 5 1MRK 505 345-UEN B Configuring the IED and changing settings The following parameter shall be set for every current transformer connected to the IED: Table 8: CT configuration Parameter description Parameter name Range Default Rated CT primary current in A CTPRIMn from 0 to 99999 3000...
  • Page 59: Establishing Connection And Verifying The Spa/Iec Communication

    1MRK 505 345-UEN B Section 6 Establishing connection and verifying the SPA/IEC communication Section 6 Establishing connection and verifying the SPA/IEC communication Entering settings M11735-2 v1 If the IED is connected to a monitoring or control system via the rear SPA/IEC port, the SPA/IEC port has to be set either for SPA or IEC use.
  • Page 60: Verifying The Communication

    Section 6 1MRK 505 345-UEN B Establishing connection and verifying the SPA/IEC communication When the setting is entered the IED restarts automatically. After the restart the selected IEC port operates as an IEC port. Set the slave number and baud rate for the rear IEC port. The slave number and baud rate can be found on the local HMI under Main menu/ Configuration/Communication/SLM configuration/Rear optical SPA-IEC-DNP port/ IEC60870–5–103...
  • Page 61: Optical Budget Calculation For Serial Communication With Spa/Iec

    1MRK 505 345-UEN B Section 6 Establishing connection and verifying the SPA/IEC communication Table 9: Max distances between IEDs/nodes glass < 1000 m according to optical budget plastic < 25 m (inside cubicle) according to optical budget Optical budget calculation for serial communication with SPA/IEC M11736-4 v2 Table 10:...
  • Page 63: Establishing Connection And Verifying The Lon Communication

    1MRK 505 345-UEN B Section 7 Establishing connection and verifying the LON communication Section 7 Establishing connection and verifying the LON communication Communication via the rear ports M12196-2 v1 7.1.1 LON communication M12196-4 v4 LON communication is normally used in substation automation systems. Optical fiber is used within the substation as the physical communication link.
  • Page 64: The Lon Protocol

    Section 7 1MRK 505 345-UEN B Establishing connection and verifying the LON communication Table 11: Specification of the fiber optic connectors Glass fiber Plastic fiber Cable connector ST-connector snap-in connector Cable diameter 62.5/125 m 1 mm Max. cable length 1000 m 10 m Wavelength 820-900 nm...
  • Page 65 1MRK 505 345-UEN B Section 7 Establishing connection and verifying the LON communication M11888-3 v4 The setting parameters for the LON communication are set via the local HMI. Refer to the technical manual for setting parameters specifications. The path to LON settings in the local HMI is Main menu/Configuration/Communication/SLM configuration/Rear optical LON port If the LON communication from the IED stops, caused by setting of illegal communication parameters (outside the setting range) or by another disturbance, it is possible to reset the...
  • Page 66: Optical Budget Calculation For Serial Communication With Lon

    Section 7 1MRK 505 345-UEN B Establishing connection and verifying the LON communication Optical budget calculation for serial communication with LON M11737-4 v2 Table 16: Example Distance 1 km Distance10 m Glass Plastic Maximum attenuation -11 dB - 7 dB 4 dB/km multi mode: 820 nm - 62.5/125 um 4 dB 0.3 dB/m plastic: 620 nm - 1mm...
  • Page 67: Establishing Connection And Verifying The Iec 61850 Communication

    1MRK 505 345-UEN B Section 8 Establishing connection and verifying the IEC 61850 communication Section 8 Establishing connection and verifying the IEC 61850 communication Overview SEMOD172103-4 v6 The rear OEM ports are used for: • process bus (IEC 61850-9-2LE) communication •...
  • Page 68: Verifying The Communication

    Section 8 1MRK 505 345-UEN B Establishing connection and verifying the IEC 61850 communication Navigate to: Main menu/Configuration/Communication/Ethernet configuration/ PRP:1 Operation , IPAddress and IPMask . Operation must be set to On . Set values for The IED will restart after confirmation. Menu items LANAB:1 and LANCD:1 are hidden in local HMI after restart but are visible in PST where the values for Mode is set to Duo .
  • Page 69: Testing Ied Operation

    1MRK 505 345-UEN B Section 9 Testing IED operation Section 9 Testing IED operation Preparing for test IP336-1 v1 9.1.1 Requirements M11740-2 v8 IED test requirements: • Calculated settings • Application configuration diagram • Signal matrix (SMT) configuration • Terminal connection diagram •...
  • Page 70: Preparing The Ied To Verify Settings

    Section 9 1MRK 505 345-UEN B Testing IED operation This IED is designed for a maximum continuous current of four times the rated current. All references to CT and VT must be interpreted as analog values received from merging units (MU) via IEC 61850-9-2LE communication protocol, analog values received from the transformer input module, or analog values received from the LDCM.
  • Page 71: Activating The Test Mode

    1MRK 505 345-UEN B Section 9 Testing IED operation release or trip from a function. Also check that the wanted recordings of analog (real and calculated) and binary signals are achieved. Parameters can be entered into different setting groups. Make sure to test functions for the same parameter setting group.
  • Page 72: Connecting The Test Equipment To The Ied

    Section 9 1MRK 505 345-UEN B Testing IED operation handle only needs to be moved from the test switch of one protection IED to the test switch of the other, without altering the previous connections. Use COMBITEST test system to prevent unwanted tripping when the handle is withdrawn, since latches on the handle secure it in the half withdrawn position.
  • Page 73: Releasing The Function To Be Tested

    1MRK 505 345-UEN B Section 9 Testing IED operation IN (I4,I5) UN (U4,U5) TRIP L1 TRIP L2 TRIP L3 IEC 61850 IEC09000652-1-en.vsd IEC09000652 V1 EN-US Figure 10: Connection example of the test equipment to the IED when test equipment is connected to the transformer input module Releasing the function to be tested M11413-2 v6...
  • Page 74: Verifying Analog Primary And Secondary Measurement

    Section 9 1MRK 505 345-UEN B Testing IED operation Verifying analog primary and secondary measurement M11745-2 v13 Verify that the connections are correct and that measuring and scaling is done correctly. This is done by injecting current and voltage to the IED. Besides verifying analog input values from the merging unit via the IEC/UCA 61850-9-2LE process bus, analog values from the transformer input module can be verified as follows.
  • Page 75: Testing The Protection Functionality

    1MRK 505 345-UEN B Section 9 Testing IED operation IEC10000032-1-en.vsd IEC10000032 V1 EN-US Figure 11: PCM600 report tool display after communication interruption Testing the protection functionality GUID-125B6F28-D3E5-4535-9CD6-6C056B79F496 v2 Each protection function must be tested individually by secondary injection. • Verify operating levels (trip) and timers. •...
  • Page 76: How To Enable Forcing

    Section 9 1MRK 505 345-UEN B Testing IED operation 9.8.2 How to enable forcing GUID-50280F59-A98C-4E48-AB6D-2B4C138943DD v1 To enable forcing, the IED must first be put into IED test mode. While the IED is not in test mode, the LHMI/PCM600 menus that relate to forcing will not have any effect on the input/ output status due to safety reasons.
  • Page 77 1MRK 505 345-UEN B Section 9 Testing IED operation IEC15000021 V1 EN-US Figure 12: Value line of the desired signal Use the up/down arrows on the LHMI to change the signal value or the appropriate menu in PCM600. The status of the signal changes automatically to Forced (i.e. there is no need to set the status to Forced manually).
  • Page 78: Forcing By Using Pcm600

    Section 9 1MRK 505 345-UEN B Testing IED operation IEC15000020 V1 EN-US Figure 13: Example of LHMI menu using BIM3 The signal “freezes” and will not change value even if, for example, a binary input signal voltage changes level, or if a binary output is activated as the result of a protection function block activating.
  • Page 79: How To Undo Forcing Changes And Return The Ied To Normal Operation

    1MRK 505 345-UEN B Section 9 Testing IED operation IEC15000025 V1 EN-US Select and edit the values. Acknowledge and send . Click IEC15000026 V1 EN-US This commits the values to the IED and exits the editing session. Click Cancel to abort the changes and revert back to actual IED values. IEC15000032 V1 EN-US Regardless if the forcing changes are commited or canceled, the forcing is still active.
  • Page 80: Undo Forcing By Using Testmode Component

    Section 9 1MRK 505 345-UEN B Testing IED operation 9.8.4.1 Undo forcing by using TestMode component GUID-CA5CCA57-DFFF-4362-AC1D-08738D2BA45F v1 • If the IED test mode was entered through the test mode function block: Deactivate the control input on that block. This immediately undoes all forcing, regardless of how it was accomplished and disabled all the way to force signals.
  • Page 81: Section 10 Testing Functionality By Secondary Injection

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Section 10 Testing functionality by secondary injection 10.1 Testing disturbance report 10.1.1 Introduction M17101-2 v6 The following sub-functions are included in the disturbance report function: • Disturbance recorder • Event list •...
  • Page 82: Event Recorder (Er) And Event List (El)

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Evaluation of the results from the disturbance recording function requires access to a PC either permanently connected to the IED or temporarily connected to the Ethernet port (RJ-45) on the front. The PCM600 software package must be installed in the PC. Disturbance upload can be performed by the use of PCM600 or by any third party tool with IEC 61850 protocol.
  • Page 83: Verifying The Settings

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10.3.1.1 Verifying the settings SEMOD55257-46 v5 Connect single-phase or three-phase test set to inject the operating voltage. The injection is done across the measuring branch. The required trip and alarm voltage, as well as the used stabilizing resistance value must be set in the function.
  • Page 84: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Switch on the current and note the operate time. Connect the test set to terminal L1 and neutral of the three-phase current input Idmin setting in the configured to REFPDIF. Also inject a current higher than half the neutral-to-earth circuit with the same phase angle and with polarity corresponding to an internal fault.
  • Page 85: Verifying The Settings

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Phase L2: × Ð ° IDiff IBias 1 240 injected L EQUATION1459 V1 EN-US Phase L3: IDiff = IBias EQUATION1460 V2 EN-US 10.3.3.1 Verifying the settings SEMOD56264-69 v4 Procedure Block the trip signal from all involved IEDs with local operation released.
  • Page 86: Additional Security Logic For Differential Protection Ldrgfc

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection After finishing a loop test with line in service and before leaving test mode, ReleaseLocal in local HMI under: Main menu/Test/Line differential the setting BlockAll . If not, the load current might test/LineDiffLogic must be set to cause incorrect operation of the differential function at restarts of the line differential protection IED.
  • Page 87: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Connect the test set for three phase voltage injection (L1, L2, L3) or residual voltage injection (N) to the appropriate IED terminals. This is dependent on how the IED is fed from the CT .
  • Page 88 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection • One phase-to-phase fault • One phase-to-earth fault The shape of the operating characteristic depends on the values of the setting parameters. The figures illustrating the characteristic for the distance protection function can be used for settings with and without load encroachment.
  • Page 89 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Test point Reach Set value Comments RLdFw –0.2143 x RFPP/2 Exact: 0.8 x RFPP/2 (ArgDir=20°) 0.8 x RFPP/2 –0.4 x RLdFw x tan(ArgDir=20°) 0.4 x RLdFw 0.5 x X1 Exact –0.5 x R1 x tan(ArgNegRes=30°) –0.23 x X1...
  • Page 90: Measuring The Operating Limit Of Set Values

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Test point Reach Value Comments 0.8 x (2 x X1 + X0 0.8 x (2 x R1 + R0 +RFPE 0.5 x (2 x X1 + R0 0.5 x (2 x R1 )/3 + RFPE 0.85 x RFPE...
  • Page 91: Measuring The Operating Time Of Distance Protection Zones

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Test points 8, 9. 10 and 11 are intended to test the directional lines of impedance protection. Since directionality is a common function for all 5 measuring zones, it is only necessary to test points 8, 9. 10 and 11 once in the forward direction in order to test the accuracy of directionality (directional angles).
  • Page 92 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection loop 60° ArgNegRes loop 50% of RLdFw RFFwPE IEC09000734-4-en.vsd IEC09000734 V4 EN-US Figure 16: Operating characteristic for phase selection function, forward direction single-phase faults Table 19: Test points for phase-to-earth loop L3-E (Ohm/loop) Test point Reach Value...
  • Page 93: Measuring The Operating Limit Of Set Values

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection phase ArgLd ArgNegRes 60° phase ArgDir 50% RLdFw 0.5·RFFwPP IEC09000735-3-en.vsd IEC09000735 V3 EN-US Figure 17: Operating characteristic for phase selection function, forward direction phase-to-phase faults Table 20: Test points for phase-to-phase loops L1–L2 (Ohm/phase) Test point Reach Value...
  • Page 94: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Supply the IED with healthy conditions for at least two seconds. Apply the fault condition and slowly decrease the measured impedance to find the operate value for of the phase-to-earth loop L3, test point 1, according to figure 16. Compare the result of the measurement with the expected value according to table 19.
  • Page 95: Phase-To-Phase Faults

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10.4.3.1 Phase-to-phase faults M14944-292 v8 ZAngPP Ohm/phase IEC07000009-4-en.vsd IEC07000009 V4 EN-US Figure 18: Proposed test points for phase-to-phase fault Table 21: Test points for phase-to-phase (ohms / phase) Test reach Value Comments...
  • Page 96: Faulty Phase Identification With Load Encroachment Fmpspdis

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection ZAngPE Ohm/loop IEC07000010-4-en.vsd IEC07000010 V4 EN-US Figure 19: Proposed test points for phase-to-earth faults Table 22: Test points for phase-to-earth loops L1-L2 (Ohm/Loop) Test Reach Value Comments points ZPE · sin(ZAngPE) ZPE ·...
  • Page 97 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Ensure that the maximum continuous current in an IED does not exceed four times its rated value, if the measurement of the operating characteristics runs under constant voltage conditions. The test procedure has to take into consideration that the shaped load encroachment characteristic is active.
  • Page 98 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection X1+XN 120° R (Ohm/loop) 20° 40% of RLdFw 80% of RLdFw alt. 80% of RFPE RFPE (Load encroachment) IEC05000369-3-en.vsd IEC05000369 V3 EN-US Figure 21: Distance protection characteristic with test points for phase-to-earth measurements Table is used in conjunction with figure 21.
  • Page 99: Measuring The Operating Limit Of Set Values

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Test point Reach Set value Comments 0.5 x X1 0.5 x R1 Only used when OperationLdCmp setting is 0 (Off) 0.5 x RFPP Table 24: Test points for phase-to-earth L3-E (Ohm/Loop) Test point Reach Value...
  • Page 100: Measuring The Operating Time Of Distance Protection Zones

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Subject the IED to healthy normal load conditions for at least two seconds. Apply the fault condition and slowly decrease the measured impedance to find the operating value of the phase-to-phase fault for zone 1 according to test point 1 in figure and table 23.
  • Page 101 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection loop 60° ArgNegRes loop 50% of RLdFw RFFwPE IEC09000734-4-en.vsd IEC09000734 V4 EN-US Figure 22: Operating characteristic for phase selection function, forward direction single-phase faults phase ArgLd ArgNegRes 60° phase ArgDir 50% RLdFw 0.5·RFFwPP...
  • Page 102: Measuring The Operating Limit Of Set Values

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Test point Value Comments 0.85·[X1+XN] R≈0.491·(X1+XN)+RFFwPE 0.85·[X1+XN]·1/tan(60°)+RFFwPE 0.85·[X1+XN] -0.85·[X1+XN]· tan (AngNegRes-90°) RFFwPE·tan (ArgLd) RFFwPE -0.5·RLdFw·tan (ArgDir) 0.5·RLdFw The table showing test points for phase-to-earth loops is used together with figure 22. Table 26: Test points for phase-to-phase loops L1–L2 Test point Value...
  • Page 103: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection When the load encroachment characteristic is deliberately set very high in order not to have an influence, then the test points 2 and 5 can be replaced by test point 7. Repeat steps to find the operate value for the phase-to-phase fault in L1 —...
  • Page 104 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 120° R (Ohm/phase) 20° 40% of RLdFw 80% of RLdFw 0.5 x RFPP IEC05000368-3-en IEC05000368 V3 EN-US Figure 24: Distance protection characteristic with test points for phase-to-phase measurements Table 27: Test points for phase-to-phase loops L1-L2 (Ohm/Loop) Test point Reach...
  • Page 105 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Test point Reach Set value Comments 0.5 x X1 0.5 x R1 0.5 x RFPP Table is used in conjunction with figure 24. X1+XN 120° R (Ohm/loop) 20° 40% of RLdFw 80% of RLdFw alt.
  • Page 106: Measuring The Operating Limit Of Set Values

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Test point Reach Value Comments RLdFw –02143 x RLdFw Exact: 0.8 x RFPE x tan (ArgDir=20°) 0.8 x RLdFw –0.8 x RLdFw tan(ArgDir=20°) –0.8 x RLdFwd tan(ArgDir=20°) 0.8 x RLdFw 0.17 x (2 x X1 + X0 Exact: 0.5 x (2 x X1...
  • Page 107: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Subject the IED to healthy normal load conditions for at least two seconds. Apply the fault condition to find the operating time for the phase-to-phase fault according to test point 12 in figure and table for zone 1.
  • Page 108 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 120° R (Ohm/phase) 20° 40% of RLdFw 80% of RLdFw 0.5 x RFPP IEC05000368-3-en IEC05000368 V3 EN-US Figure 26: Distance protection characteristic with test points for phase-to-phase measurements Table 29: Test points for phase-to-phase loops L1-L2 (Ohm/Loop) Test point Reach Set value...
  • Page 109 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Test point Reach Set value Comments 0.5 x X1 0.5 x R1 0.5 x RFPP Table is used in conjunction with figure 26. X1+XN 120° R (Ohm/loop) 20° 40% of RLdFw 80% of RLdFw alt.
  • Page 110: Measuring The Operating Limit Of Set Values

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Test point Reach Value Comments RLdFw –02143 x RLdFw Exact: 0.8 x RFPE x tan (ArgDir=20°) 0.8 x RLdFw –0.8 x RLdFw tan(ArgDir=20°) 0.8 x RLdFw 0.17 x (2 x X1 + X0 Exact: 0.5 x (2 x X1 -0.36 x (2 x X1...
  • Page 111: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Subject the IED to healthy normal load conditions for at least two seconds. Apply the fault condition to find the operating time for the phase-to-phase fault according to test point 10 in figure and table for zone 1.
  • Page 112: Verifying The Settings

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection X1OutFw X1InFw RLdOutRv RLdOutFw RLdInRv RLdInFw X1InRv X1OutRv IEC09000226_1_en.vsd IEC09000226 V1 EN-US Figure 28: Operating principle and characteristic of the power swing detection function (settings parameters in italic) Where: RLdOutFw ·...
  • Page 113: Testing The Power Swing Detection Function Zmrpsb

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Decrease the measured three-phase impedance slowly and observe the operation value for the signal ZOUT. Compare the operation value with the set value. Do the necessary change of the setting of the test equipment and repeat step and step for point 2, 3 and 4 according to figure 28.
  • Page 114: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection If the input I0CHECK is configured (connected to output signal STPE on FDPSPDIS or FRPSPDIS, the test of inhibit of ZMRPSB at earth-fault during power swing can be done in tR1 .
  • Page 115: Testing The Influence Of The Residual Overcurrent Protection

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10.4.10.2 Testing the influence of the residual overcurrent protection M14946-28 v5 Additionally connect the IED according to the test instructions for the four step residual overcurrent protection function EF4PTOC, if the Power swing logic (PSLPSCH) is configured in a way that is controlled by this protection.
  • Page 116: Verifying The Settings

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.4.11.1 Verifying the settings SEMOD175096-7 v3 It is assumed that setting of the pole slip protection function PSPPPAM is done according to impedances as seen in figure and figure 30. The test is done by means of injection of three-phase current and three-phase voltage from a modern test device.
  • Page 117 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Zone 1 Zone 2 X’ Pole slip impedance movement Zone 2 TripAngle Zone 1 WarnAngle IEC07000099_2_en.vsd IEC07000099 V2 EN-US Figure 29: Setting of the pole slip protection PSPPPAM Commissioning manual...
  • Page 118: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Imin > 0.10 IBase Umax < 0.92 UBase START 0.2 £ f(Ucos) £ 8Hz d ³ StartAngle ZONE1 Z cross line ZA - ZC ZONE2 Z cross line ZC - ZB Counter b a ³...
  • Page 119: Verifying The Settings

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10.4.12.1 Verifying the settings GUID-708C4033-3111-481F-9868-FF207C18C9F9 v1 The test of the out-of-step protection function is made to verify that the trip is issued if the following events happen. • the impedance, seen by the function, enters the lens characteristic from one side and leaves it from the opposite side TripAngle and tBreaker •...
  • Page 120 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 2 5 8367 20918 × × Base (Equation 3) EQUATION14043 V1 EN-US ReachZ1 defines the boundary between zone 1 and zone 2; it is expressed in The parameter ForwardX . If the setting of ReachZ1 = 12% , then corresponding percent of the parameter primary value of the reactance is ReachZ...
  • Page 121 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection The previous calculations are in primary values. They are transferred to secondary values to perform injections by a test set. Primary values are transferred to secondary values by taking into account the CT ratio and the VT ratio (respectively 9000/1 A and 13.8/0.1 kV in the example).
  • Page 122: Test Of Point Re (R Fwdr , X Fwdx )

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection • 49.5 Hz for the test as generator in the quadrant 1 and 2 of the R-X plane • 50.5 Hz for the test as generator in the quadrant 3 and 4 of the R-X plane When the trajectory of the impedance, that is seen by the protection function, traverses the lens characteristic then a pole slipping is detected.
  • Page 123 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection ForwardX 59 33     arctan arctan 82. . 14° ∠  =  =   ForwardR 8 19     (Equation 18) EQUATION14058 V1 EN-US frequency of V = 50 Hz 10459...
  • Page 124 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection VT s 1 1 11931 95 1 × × × × t FwdZ 13 8 VT p (Equation 23) EQUATION14057 V1 EN-US ForwardX 59 33     arctan arctan 82.
  • Page 125 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection frequency of = 50 Hz • Check that the service values (VOLTAGE, CURRENT, R(%), X(%) ) are according to the injected quantities and that ROTORANG is close to 3.14 rad. For this particular injection the service values are: •...
  • Page 126: Test Of The Boundary Between Zone 1 And Zone 2, Which Is Defined By The Parameter Reachz1

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10459 1 162 × × 9000 (Equation 36) EQUATION14062 V1 EN-US ∠I = 180º frequency of I = 49.5 Hz Expected result: start of the protection function and trip in zone 2, when trip conditions are fulfilled.
  • Page 127 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Note that these values identify a point inside the lens characteristic, in the Zone 2, that is close to the boundary between zone 1 and zone 2. The START is issued, but no TRIP is performed. Execution of the dynamic test GUID-53964189-42E4-4C4B-BFCD-64888BA938EF v1 The test may be performed by using two states of a sequence tool that is a basic feature of...
  • Page 128 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection The trajectory of the impedance traverses the lens characteristic in zone 1 GUID-12F82DD8-A4CE-48C9-944B-0CF3B3F6C9F9 v1 Preliminary steady state test at 50 Hz GUID-AA953F5F-2389-4F05-8BBD-D8DC9AF3B0E4 v1 • Go to Main menu/Test/Function status/Impedance protection/OutOfStep(78,Ucos)/ OOSPPAM(78,Ucos):1/Outputs to check the available service values of the function block OOSPPAM.
  • Page 129: Test Of The Point Se (R Rvsr , X Rvsx )

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection VT s 0 9 1435 9 36 × × × × t RZ 13 8 VT p (Equation 51) EQUATION14066 V1 EN-US ForwardX 59 33     arctan arctan 82.
  • Page 130 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection VT s 0 9 5899 38 47 × × × × t RvsZ 13 8 VT p (Equation 57) EQUATION14067 V1 EN-US æ ö æ ö ReverseX 29.60 Ð °...
  • Page 131 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection • State 2: main test step. Define the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 0 9 5899 38 47 × × ×...
  • Page 132 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10459 1 162 × × 9000 (Equation 70) EQUATION14062 V1 EN-US ∠ = 0º frequency of = 50 Hz • Check that the service values (VOLTAGE, CURRENT, R(%), X(%)) are according to the injected quantities and that ROTORANG is close to 0 rad.
  • Page 133: Automatic Switch Onto Fault Logic Zcvpsof

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10459 1 162 × × 9000 (Equation 75) EQUATION14059 V1 EN-US ∠I = 0º frequency of I = 50 Hz 10459 1 162 × × 9000 (Equation 76) EQUATION14062 V1 EN-US ∠I = 180º...
  • Page 134: Activating Zcvpsof Externally

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection ZCVPSOF is activated either by the external input BC, or by the internal DLD. FUFSPVC is done with a pre-fault condition where the phase voltages and currents are at zero. A reverse three- phase fault with zero impedance and a three-phase fault with an impedance corresponding to the whole line is applied.
  • Page 135: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection quadrilateral characteristic function ZMQPDIS. The distance protection and the phase preference logic shall be set to values according to the real set values to be used. The test is made by means of injection of voltage and current where the amplitude of both current and voltage and the phase angle between the voltage and current can be controlled.
  • Page 136: Measuring The Operate Limit Of Set Values

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Ensure that the maximum continuous current, supplied from the current source used for the test of the IED, does not exceed four times the rated current value of the IED. 10.5.1.1 Measuring the operate limit of set values M11754-11 v6...
  • Page 137: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 3.1. Set the injected polarizing voltage slightly larger than the set minimum polarizing voltage (default is 5% of UBase ) and set the injection current to lag the appropriate voltage by an angle of about 80°...
  • Page 138: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Inject a phase current into the IED with an initial value below that of the setting. Increase the injected current in the Ln or in the neutral (summated current input) phase until the TRIP signal appears.
  • Page 139: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Do as described in "Four step directional earth fault protection", but without applying any polarizing voltage. 10.5.4.3 Completing the test SEMOD53296-122 v4 TestMode setting to Off . Continue to test another function or end the test by changing the Restore connections and settings to their original values, if they were changed for testing purposes.
  • Page 140: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.5.5.1 Completing the test SEMOD53296-122 v4 TestMode setting to Off . Continue to test another function or end the test by changing the Restore connections and settings to their original values, if they were changed for testing purposes.
  • Page 141 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection The I Dir (3I · cosφ) function activates the START and STDIRIN output. Assume that φ´ is the phase angle between injected voltage (3U ) and current (3I ) i.e. φ RCADir -φ.
  • Page 142 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection RCADir = 0º Operate area Instrument transformer  angle error RCAcomp Characteristic after angle compensation (to prot) (prim) IEC06000651-3-en.vsd IEC06000651 V3 EN-US Figure 35: Explanation of RCAcomp Operation mode 3I ·...
  • Page 143 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Operation mode 3I and φ SEMOD175060-87 v8 UNRel> and set the phase angle between voltage and Set the polarizing voltage to 1.2 · RCADir ). Note that the current lagging the voltage. current to the set characteristic angle ( Inject current until the function picks up, and make sure that the operate current is equal INDir>...
  • Page 144: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection tINNonDir or inverse time was The expected value depends on whether definite time selected. Off . Continue to test another function or complete the test by setting the test mode to Residual overvoltage release and protection SEMOD175060-131 v6 Procedure...
  • Page 145: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Check the reset limit (TdReset). Monitor the signal START until it disappears on the corresponding binary output or on ReclTemp . the local HMI, take the TEMP readings and compare with the setting of Compare the measured trip time with the setting according to the formula.
  • Page 146: Checking The Re-Trip And Back-Up Times

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Apply the fault condition, including START of CCRBRF, with a current just below set IN> . Repeat the fault condition and increase the current in steps until trip appears. IN>...
  • Page 147: Verifying Instantaneous Back-Up Trip At Cb Faulty Condition

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Checking that back-up tripping is not achieved at normal CB tripping M12104-150 v7 Use the actual tripping modes. The case below applies to re-trip with current check. Apply the fault condition, including start of CCRBRF, with phase current well above set IP>...
  • Page 148: Verifying The Function Mode Current&Contact

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Verify that phase selection re-trip and back-up trip are achieved after set times. Disconnect the start signal(s). Keep the CB closed signal(s). Apply input signal(s), for start of CCRBRF. t2 .
  • Page 149: Measuring The Operate Limit Of Set Values

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10.5.9.1 Measuring the operate limit of set values M14922-6 v8 Check that the input logical signals BLOCK and RELEASE and the output logical signal TRIP are all logical zero. Activate the input RELEASE on the STBPTOC function block For a short while inject a current (fault current) in one phase to about 110% of the set operating current, and switch the current off.
  • Page 150: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection selection = ContSel setting equals Pole If Internal detection logic Contact function position from auxiliary contacts. Then set inputs POLE1OPN...POLE3CL in a status that activates the pole discordance logic and repeats step 2 to step 6. Unsymmetrical current detection with CB monitoring: Set measured current in one phase to 110% of current release level.
  • Page 151 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Table 32: Calculation modes Mode Set value: Formula used for complex power calculation L1, L2, L3 × × × (Equation 80) EQUATION1697 V1 EN-US Arone × × (Equation 81) EQUATION1698 V1 EN-US PosSeq = ×...
  • Page 152: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.5.11.2 Completing the test SEMOD175027-15 v4 TestMode setting to Off . Continue to test another function or end the test by changing the Restore connections and settings to their original values, if they were changed for testing purposes.
  • Page 153: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Check that the input logical signal BLOCK to the BRCPTOC function block is logical zero and note on the local HMI that the output signal TRIP from the BRCPTOC function block is equal to the logical 0.
  • Page 154 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection UBase ≤ Restrain voltage ≤ UHighLimit / Second part of the characteristic (25% of 100* UBase ), valid when setting parameter VDepMode = Slope :  StartCurr VDepFact  ...
  • Page 155 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Repeat steps 4 and 5 applying voltages that are related to the second and the last section of the characteristic; the function operates when IL1 is slightly higher than: 0.5 A in the second section;...
  • Page 156: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection If the VRPVOC function is used as an overcurrent protection with undervoltage seal-in, it is necessary to first inject sufficient current to activate the STOC signal before the under-voltage step is allowed to operate.
  • Page 157: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection UBase VT < × × VTprim (Equation 94) IECEQUATION2430 V1 EN-US For phase-to-phase measurement: < UBase × × VTprim (Equation 95) IECEQUATION2431 V1 EN-US Increase the measured voltage to rated load conditions. Check that the START signal resets.
  • Page 158: Extended Testing

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Verification of single-phase voltage and time delay to operate for Step 1 M13806-50 v8 U1> . Apply single-phase voltage below the set value Slowly increase the voltage until the ST1 signal appears. U1>...
  • Page 159: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Measure the time delay for the TR1 signal and compare it with the set value. Check the inverse time delay by injecting a voltage corresponding to 1.2 × U1>. For example, if the inverse time curve A is selected, the trip signals TR1 and TRIP operate after a time corresponding to the equation: ...
  • Page 160: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Set the cooling time constant temporarily to min value (1min.) to quickly lower the thermal content. Tcooling switch 20 minutes on a voltage 1.15 · V/Hz> Wait for a period equal to 6 times and check the inverse operate time.
  • Page 161 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection IEC07000106-1-en.vsd IEC07000106 V2 EN-US Figure 37: Connection of the test set to the IED for test of U1 block level where: is three-phase voltage group1 (U1) is three-phase voltage group2 (U2) Decrease slowly the voltage in phase UL1 of the test set until the START signal resets.
  • Page 162: Check Of Voltage Differential Trip And Alarm Levels

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection IEC07000107-1-en.vsd IEC07000107 V2 EN-US Figure 38: Connection of the test set to the IED for test of U2 block level where: is three-phase voltage group1 (U1) is three-phase voltage group2 (U2) UDTrip , U1Low and U2Low to the U1 Apply voltage higher than the highest set value of three-phase inputs and to one phase of the U2 inputs according to figure 38.
  • Page 163: Check Of Trip And Trip Reset Timers

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection IEC07000108-1-en.vsd IEC07000108 V2 EN-US Figure 39: Connection of the test set to the IED for test of alarm levels, trip levels and trip timer where: is three-phase voltage group1 (U1) is three-phase voltage group2 (U2) Apply 1.2 ·...
  • Page 164: Final Adjustment Of Compensation For Vt Ratio Differences

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection tTrip . Check the measured time by comparing it to the set trip time Increase the voltage until START signal resets. Measure the time from reset of START signal to reset of TRIP signal. tReset .
  • Page 165: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Activate the VTSU binary input. Simultaneously disconnect all the three-phase voltages from the IED. No TRIP signal should appear. Reset the VTSU binary input. tRestore time. Inject the measured voltages at rated values for at least set Activate the BLOCK binary input.
  • Page 166: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection • Check that TRIP and TRL1 are generated with the conditions described after a set delay t1Ph and the outputs ARST and ARSTL1 are also activated. . time of •...
  • Page 167: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Check that the START signal resets. Instantaneously decrease the frequency of the applied voltage to a value about 1% lower than the operate value (a step change more than 2% will increase the time delay). Measure the time delay of the TRIP signal, and compare it with the set value.
  • Page 168: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection The test above can be repeated to check the time to reset. Verification of the low voltage magnitude blocking M16290-34 v5 StartFrequency , UMin , Check that the settings in the IED are appropriate, for example the tDelay .
  • Page 169: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10.7.3.2 Completing the test M16256-39 v4 TestMode setting to Off . Continue to test another function or end the test by changing the Restore connections and settings to their original values, if they were changed for testing purposes.
  • Page 170: Overcurrent Feature With Current Restraint

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Information on how to use the event menu is found in the operator's manual. 10.8.1.2 Overcurrent feature with current restraint SEMOD56488-35 v3 The current restraining value has also to be measured or calculated and the influence on the operation has to be calculated when the testing of the operate value is done.
  • Page 171: Over/Undervoltage Feature

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection CTstarpoint configuration parameter is set to If reverse directional feature is selected or FromObject , the angle between current and polarizing voltage shall be set equal to rca- dir+180°. Overall check in principal as above (non-directional overcurrent feature) Reverse the direction of the injection current and check that the protection does not operate.
  • Page 172: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.9.1.2 Completing the test M12917-43 v4 TestMode setting to Off . Continue to test another function or end the test by changing the Restore connections and settings to their original values, if they were changed for testing purposes.
  • Page 173: Measuring The Operate Value For The Zero-Sequence Function

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Simulate normal operating conditions with the three-phase currents in phase with their corresponding phase voltages and with all of them equal to their rated values. Slowly decrease the measured voltage in one phase until the BLKU signal appears. Record the measured voltage and calculate the corresponding negative-sequence voltage according to the equation (observe that the voltages in the equation are phasors): ⋅...
  • Page 174: Measuring The Operate Value For The Dead Line Detection Function

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection × (Equation 106) IEC00000276 V1 EN-US Where: and U are the measured phase voltages IEC00000275 V1 EN-US Compare the result with the set value of the zero-sequence operating voltage (consider that the set value 3U0>...
  • Page 175: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection The BLKU, BLKZ and 3PH signals should reset, if activated, see step and 2. Change the voltages and currents in all three phases simultaneously. DU> and the current change must The voltage change must be higher than the set value DI<...
  • Page 176: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection After more than 5 seconds increase the measured voltage back to the value slightly below USealIn level. MAINFUF signal should not reset. USealIn until MAINFUF signal Slowly increase measured voltage to the value slightly above resets.
  • Page 177: Testing The Synchronizing Function

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Test UMeasure U-Bus U3PBB1 Ph/N equipment Ph/Ph Input Phase L1,L2,L3 L12,L23,L31 UMeasure U-Line Ph/N U3PLN1 Ph/Ph Input Phase L1,L2,L3 L12,L23,L31 IEC05000480-4-en.vsd IEC05000480 V4 EN-US Figure 40: General test connection with three-phase voltage connected to the line side U-Bus1 Test UMeasure...
  • Page 178: Testing The Synchrocheck Check

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Testing the frequency difference M2377-116 v10 The frequency difference test should verify that operation is achieved when the frequency FreqDiffMax and above set value of difference between bus and line is less than set value of FreqDiffMin .
  • Page 179 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Testing the phase angle difference M2377-215 v8 The phase angle differences PhaseDiffM and PhaseDiffA respectively are set to their final settings and the test should verify that operation is achieved when the phase angle difference is lower than this value both leading and lagging.
  • Page 180: Testing The Energizing Check

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Testing the reference voltage M2377-249 v5 Use the same basic test connection as in figure 40. The voltage difference between the voltage connected to U-Bus and U-Line should be 0%, so that the AUTOSYOK and MANSYOK outputs are activated first.
  • Page 181: Testing The Voltage Selection

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Verify the local HMI settings AutoEnerg or ManEnerg to be Both . GblBaseSelLine to the U-Line and a single-phase Apply a single-phase voltage of 30% GblBaseSelBus to the U-Bus. voltage of 100% tAutoEnerg Check that the AUTOENOK and MANENOK outputs are activated after set...
  • Page 182 Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Testing the voltage selection for 1 1/2 CB arrangements GUID-12E7DA63-FE04-4C83-9BA6-34818C510DB8 v4 At test of the SESRSYN function for a 1½ CB diameter the following alternative voltage inputs can be used for the three SESRSYN (SESRSYN 1, SESRSYN 2, SESRSYN 3) functions. These three SESRSYN functions can either be in one, two or three different IEDs.
  • Page 183: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection WA1_QA1 WA2_QA1 (SESRSYN 1) (SESRSYN 3) TIE_QA1 (SESRSYN 2) LINE1_QB9 LINE2_QB9 LINE1 LINE2 IEC11000274-3-en.vsd IEC11000274 V3 EN-US Figure 43: Objects used in the voltage selection logic 10.10.1.5 Completing the test M2377-1042 v5 TestMode setting to Off .
  • Page 184 1MRK 505 345-UEN B Testing functionality by secondary injection external bi-stable relay (BR), for example a relay type RXMVB2 or RXMD or Breaker Simulator of ABB. The following manual switches are used: • Switch or push-button to close (SC) •...
  • Page 185: Preparation Of The Verification

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection CLOSE CB Trip CB POS CB READY To test IEC04000202-1- en.vsd IEC04000202 V2 EN-US Figure 44: Simulating the CB operation by a bi-stable relay/breaker simulator and manual switches 10.10.2.1 Preparation of the verification M12400-40 v7 Check the function settings on the local HMI under Main menu/Settings/Setting group...
  • Page 186: Verifying The Autorecloser Function Smbrrec

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection The CB should be closed and ready. If external control inputs OFF/ON are used, check that they work. Set ExternalCtrl = On and use the control inputs to switch On and Off, and check the state of the function. 10.10.2.3 Verifying the autorecloser function SMBRREC M12400-91 v11...
  • Page 187 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Check that the autorecloser function SMBRREC is operative, for example, by making a reclosing shot without the INHIBIT signal. Apply a fault and thereby a START signal. At the same time, or during the open time, apply a signal to the input INHIBIT.
  • Page 188: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection It is also possible to verify the two functions together by using CB simulating equipment for two CB circuits. There should be interconnections from the master to the slave function, WFMASTER - WAIT, and UNSUCCL - INHIBIT, as shown in the illustration referred to above.
  • Page 189: Scheme Communication

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Values of the logical signals are available on the local HMI under Main menu/Tests/Function status/Control/Apparatus control/Interlocking. The Signal Monitoring in PCM600 shows the same signals that are available on the local HMI. The interlocking function consists of a bay-level part and a station-level part.
  • Page 190: Testing Blocking Scheme

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Apply healthy normal load conditions to the IED for at least two seconds. Apply a fault condition within the permissive zone. Check that trip time complies with the zone timers and that correct trip outputs, external signals, and indications are obtained for the actual type of fault generated.
  • Page 191: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Activate the guard input signal (CRG) of the IED. Using the scheme selected, check that a signal accelerated trip (TRIP) is obtained when the guard signal is deactivated. 10.11.1.6 Completing the test M13868-84 v6 TestMode setting to Off .
  • Page 192: Testing Blocking Scheme

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Apply healthy normal load conditions to the IED for at least two seconds. Apply a fault condition within the permissive zone. Check that trip time complies with the zone timers and that correct trip outputs, external signals, and indications are obtained for the actual type of fault generated.
  • Page 193: Weak End Infeed Logic

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Checking of current reversal M14947-13 v8 The reverse zone timer must not operate before the forward zone fault is applied. The user might need to block the reverse zone timer setting during testing of current reversal.
  • Page 194: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Apply input signals according Table 34. Activate the receive (CR) signal. After the IED has operated, turn off the input signals. Check that trip, send signal, and indication are obtained. The ECHO output gives only a 200 ms pulse.
  • Page 195: Testing The Directional Comparison Logic Function

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection communication logic for residual overcurrent protection. The current reversal and weak-end- infeed functions shall be tested together with the permissive scheme. 10.11.5.1 Testing the directional comparison logic function M13926-7 v2 Blocking scheme M13926-9 v5 UBase (EF4PTOC) where the current is lagging...
  • Page 196: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Switch the fault current on (110% of the set operating current) and wait for a period longer than the set value tCoord . No TRIP signal should appear. Switch the fault current and the polarizing voltage off. Reset the CR binary input and the BLOCK digital input.
  • Page 197 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Inject the polarizing voltage 3U0 to (180° — AngleRCA ) of UBase and the phase angle between voltage and current to 155°, the current leads the voltage. AngleRCA ) in one phase to about 110% of the setting operating Inject current (180°...
  • Page 198: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection No ECHO and TRWEI should appear. Abruptly reverse the current to 65° lagging the voltage to operate the forward directional element. No ECHO and TRWEI should appear. Switch the current off and check that the ECHO, CS and TRWEI appear on the corresponding binary output during 200ms after resetting the directional element.
  • Page 199: Compensated Over- And Undervoltage Protection Couvgapc

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Set the phase angle of the injected current slightly higher than the operate value. Switch on the current and check the time delay. Check that all trip and start contacts operate according to the configuration (signal matrices).
  • Page 200: Sudden Change In Current Variation Sccvptoc

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection Check that the line impedance (R1 and X1) and reactor impedance (Xc) are set to the correct values. Inject symmetrical phase voltages equal to 120% of the rated voltage. Increase the injected current (same phase angle as the injected voltage) in phase L1 from zero and note the operated value (start value) of the function.
  • Page 201 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection INPut LOCTR LOCTRL1 LOCTRL2 LOCTRL3 Table 36: Activate output signals if OpMode = 2 Out Of 2 OUTPut TRIP TRL1 TRL2 TRL3 Connect the trip output to a timer. Have inputs CR1and CR2 activated.
  • Page 202: Negative Sequence Overvoltage Protection Lcnsptov

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.11.7.5 Negative sequence overvoltage protection LCNSPTOV GUID-BEF622E8-E133-4346-98D4-EC0732878937 v1 Prepare the IED for verification of settings as outlined in section "Requirements" and section "Preparing for test" in this chapter. I E D T E S T S E T IEC10000014-1-en.vsd IEC10000014 V1 EN-US Figure 45: Connection of test equipment...
  • Page 203: Negative Sequence Overcurrent Protection Lcnsptoc

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Set the injected voltage to 110% of the operate level in the tested stage, switch on the current and check the time delay. Check that all trip and start contacts operate according to the configuration (signal matrices).
  • Page 204: Zero Sequence Overcurrent Protection Lczsptoc

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.11.7.8 Zero sequence overcurrent protection LCZSPTOC GUID-DF48CC20-7275-4543-84D1-0856A946520A v2 Prepare the IED for verification of settings as outlined in section "Requirements" and section "Preparing for test" in this chapter. Connect the test set for three-phase voltage injection (L1, L2, L3or residual voltage injection (N) to the appropriate IED terminals.
  • Page 205: Logic

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Decrease the injected current step-wise to 50% of the operate level and check the time delay. Check that all trip and start contacts operate according to the configuration (signal matrices).
  • Page 206: 1Ph/2Ph/3Ph Operating Mode

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection of the trip outputs (TRLn) should be activated at a time. Functional outputs TRIP and TR1P should be active during each fault. No other outputs should be active. Initiate different phase-to-phase and three-phase faults. Consider using an adequate time interval between faults, to overcome a reclaim time, which is activated by SMBRREC.
  • Page 207: Circuit Breaker Lockout

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection A single-phase fault shall be given at the first fault. A three-phase trip must be initiated for the second fault. Check that the corresponding trip signals appear after both faults. Functional outputs TRIP, TRLn and TR1P should be active during first fault.
  • Page 208: Monitoring

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.13 Monitoring SEMOD53581-1 v1 10.13.1 Gas medium supervision SSIMG GUID-0A83B4D5-51FF-43CB-8DC7-AFCEA2BC7B69 v1 Prepare the IED for verification of settings as outlined in section "Testing the liquid medium supervision for alarm and lock out conditions" and section "Completing the test"...
  • Page 209: Completing The Test

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection Activate BLOCK binary input, the signals LVL_ALM, LVL_LO should disappear. Reset the BLOCK binary input. Check for reset lock out input RESET_LO to reset the LVL_LO lock out signal. Conduct these steps for temperature input as well to detect and reset TEMP_ALM and TEMP_LO signals.
  • Page 210: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection RatedOperCurr , RatedFltCurr , OperNoRated , 6.1. Test the set timing defined by OperNoFault , DirCoef , CBLifeAlmLevel . 6.2. Vary the phase current in the selected phase from below rated operated current, RatedOperCurr to above rated fault current, RatedFltCurr of a breaker.
  • Page 211: Fault Locator Lmbrflo

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection During testing, the IED can be set when in test mode from PST. The functionality of the event reporting during test mode is set in the Parameter Setting tool in PCM600. •...
  • Page 212: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection × ------ - 100 (Equation 110) EQUATION123 V1 EN-US in % for two- and three-phase faults × × + × X0 2 X1 (Equation 111) EQUATION124 V1 EN-US in % for single-phase-to-earth faults ×...
  • Page 213: Metering

    1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection 10.14 Metering SEMOD53588-1 v1 10.14.1 Pulse-counter logic PCFCNT M13405-2 v7 The test of the Pulse-counter logic function PCFCNT requires the Parameter Setting tool in PCM600 or an appropriate connection to the local HMI with the necessary functionality. A known number of pulses with different frequencies are connected to the pulse counter input.
  • Page 214: Completing The Test

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection After 1 minute check the MAXPAFD and MAXPRFD whether it is showing the last 1 minute average power value as maximum. Next 1 minute cycle reduce the current or voltage below previous value. Check after 1 minute whether the MAXPAFD and MAXPRFD outputs are retaining the old maximum value.
  • Page 215 1MRK 505 345-UEN B Section 10 Testing functionality by secondary injection To perform a test of Binary signal transfer function (BinSignReceive/BinSignTransm), the hardware (LDCM) and binary input and output signals to transfer must be configured as required by the application. There are two types of internal self supervision of BinSignReceive/BinSignTransm •...
  • Page 216: Basic Ied Functions

    Section 10 1MRK 505 345-UEN B Testing functionality by secondary injection 10.17 Basic IED functions SEMOD52026-1 v1 10.17.1 Parameter setting group handling SETGRPS M11369-2 v3 Prepare the IED for verification of settings as outlined in section "Requirements" and section "Preparing for test" in this chapter.
  • Page 217: Section 11 Checking The Directionality

    1MRK 505 345-UEN B Section 11 Checking the directionality Section 11 Checking the directionality 11.1 Overview GUID-7E504488-F341-477A-953A-EB0B262911EB v2 Before starting this process, all individual devices that are involved in the fault clearance process of the protected object must have been individually tested and must be set in operation.
  • Page 218 Section 11 1MRK 505 345-UEN B Checking the directionality • L1Dir = Forward • L2Dir = Forward • L3Dir = Forward The following will be shown if the load current flows in the reverse direction (importing): • L1Dir = Reverse •...
  • Page 219: Section 12 Commissioning And Maintenance Of The Fault Clearing System

    The periodicity of all tests depends on several factors, for example the importance of the installation, environmental conditions, simple or complex equipment, static or electromechanical IEDs, and so on. The normal maintenance praxis of the user should be followed. However, ABB's recommendation is as follows: Every second to third year •...
  • Page 220: Visual Inspection

    ABB protection IEDs are preferably tested by aid of components from the COMBITEST testing system described in information B03-9510 E. Main components are RTXP 8/18/24 test switch usually located to the left in each protection IED and RTXH 8/18/24 test handle, which is inserted in test switch at secondary testing.
  • Page 221: Alarm Test

    1MRK 505 345-UEN B Section 12 Commissioning and maintenance of the fault clearing system specific protection IED. Only the setting values adopted shall be checked for each protection function. If the discrepancy between obtained value and requested set value is too big the setting should be adjusted, the new value recorded and a note should be made in the test record.
  • Page 222: Restoring

    Section 12 1MRK 505 345-UEN B Commissioning and maintenance of the fault clearing system recorded. Also check the direction of directional functions such as Distance and directional overcurrent functions. For transformer differential protection, the achieved differential current value is dependent on the tap changer position and can vary between less than 1% up to perhaps 10% of rated current.
  • Page 223: Section 13 Troubleshooting

    No problem detected. None. Time synch Fail No time Check the synchronization source for problems. synchronization. If the problem persists, contact your ABB representative for service. Real time clock Ready No problem detected. None. Real time clock Fail The real time clock has Set the clock.
  • Page 224: Fault Tracing

    Ready (I/O module name) I/O modules has failed. Check that the I/O module has been configured and Fail connected to the IOP1- block. If the problem persists, contact your ABB representative for service. 13.2 Fault tracing IP8765-1 v1 13.2.1 Internal fault indications...
  • Page 225: Using Front-Connected Pc

    1MRK 505 345-UEN B Section 13 Troubleshooting HMI Signal Name: Status Description Application READY / FAIL This signal will be active if one or more of the application threads are not in the state that Runtime Engine expects. The states can be CREATED, INITIALIZED, RUNNING, etc.
  • Page 226: Diagnosing The Ied Status Via The Lhmi Hint Menu

    Section 13 1MRK 505 345-UEN B Troubleshooting The internal events in this list not only refer to faults in the IED, but also to other activities, such as change of settings, clearing of disturbance reports, and loss of external time synchronization.
  • Page 227 1MRK 505 345-UEN B Section 13 Troubleshooting The Hint menu is currently only available in English. All the entries are in English, regardless of which language is selected. The supported list of hints are as follows: Table 43: Hint menu Headline Explanation Incorrect setting of SyncLostMode...
  • Page 228: Hardware Re-Configuration

    Corresponding hardware(s) is set to fail. Please restart IED and consider Reconfigure HW modules to get updated hardware list. Non ABB vendor SFP detected Non ABB vendor SFP detected. Corresponding hardware(s) is set to fail. Please use ABB approved SFP’s.
  • Page 229: Repair Instruction

    M11764-10 v1 An alternative is to open the IED and send only the faulty circuit board to ABB for repair. When a printed circuit board is sent to ABB, it must always be placed in a metallic, ESD-proof, protection bag. The user can also purchase separate replacement modules.
  • Page 230: Repair Support

    Repair support M11768-3 v3 If an IED needs to be repaired, the whole IED must be removed and sent to an ABB Logistic Center. Before returning the material, an inquiry must be sent to the ABB Logistic Center. e-mail: offer.selog@se.abb.com 13.5...
  • Page 231: Section 14 Glossary

    1MRK 505 345-UEN B Section 14 Glossary Section 14 Glossary M14893-1 v18 Alternating current Actual channel Application configuration tool within PCM600 A/D converter Analog-to-digital converter ADBS Amplitude deadband supervision Analog digital conversion module, with time synchronization Analog input ANSI American National Standards Institute Autoreclosing ASCT Auxiliary summation current transformer...
  • Page 232 Section 14 1MRK 505 345-UEN B Glossary CO cycle Close-open cycle Codirectional Way of transmitting G.703 over a balanced line. Involves two twisted pairs making it possible to transmit information in both directions Command COMTRADE Standard Common Format for Transient Data Exchange format for Disturbance recorder according to IEEE/ANSI C37.111, 1999 / IEC 60255-24 Contra-directional...
  • Page 233 1MRK 505 345-UEN B Section 14 Glossary Electromagnetic interference EnFP End fault protection Enhanced performance architecture Electrostatic discharge F-SMA Type of optical fiber connector Fault number Flow control bit; Frame count bit FOX 20 Modular 20 channel telecommunication system for speech, data and protection signals FOX 512/515 Access multiplexer...
  • Page 234 Section 14 1MRK 505 345-UEN B Glossary IEEE Institute of Electrical and Electronics Engineers IEEE 802.12 A network technology standard that provides 100 Mbits/s on twisted- pair or optical fiber cable IEEE P1386.1 PCI Mezzanine Card (PMC) standard for local bus modules. References the CMC (IEEE P1386, also known as Common Mezzanine Card) standard for the mechanics and the PCI specifications from the PCI SIG (Special Interest Group) for the electrical EMF (Electromotive force).
  • Page 235 1MRK 505 345-UEN B Section 14 Glossary National Control Centre Number of grid faults Numerical module OCO cycle Open-close-open cycle Overcurrent protection Optical Ethernet module OLTC On-load tap changer OTEV Disturbance data recording initiated by other event than start/pick-up Overvoltage Overreach A term used to describe how the relay behaves during a fault condition.
  • Page 236 Section 14 1MRK 505 345-UEN B Glossary Short circuit location Station control system SCADA Supervision, control and data acquisition System configuration tool according to standard IEC 61850 Service data unit SELV circuit Safety Extra-Low Voltage circuit type according to IEC60255-27 Small form-factor pluggable (abbreviation) Optical Ethernet port (explanation) Serial communication module.
  • Page 237 1MRK 505 345-UEN B Section 14 Glossary Transformer Module. This module transforms currents and voltages taken from the process into levels suitable for further signal processing. Type identification User management tool Underreach A term used to describe how the relay behaves during a fault condition. For example, a distance relay is underreaching when the impedance presented to it is greater than the apparent impedance to the fault applied to the balance point, that is, the set reach.
  • Page 240 ABB AB Substation Automation Products SE-721 59 Västerås, Sweden Phone +46 (0) 21 32 50 00 Scan this QR code to visit our website www.abb.com/substationautomation © Copyright 2016 ABB. All rights reserved.

This manual is also suitable for:

Relion red670

Table of Contents