4.2.3 Precautions in transportation
To prevent the device from being damaged during transportation, the original packing should be left
untouched until the device arrives near the intended installation site.
The detector is equipped with hanging hooks. Lift it as shown in Figure 4.5. For information on the
actual mass of each diameter, refer to Table 4.2.
CAUTION
(1)Never lift the detector by inserting a bar
into its measurement pipe, because this will
damage the linings, thus making it impossible
to take stable measurements.
(2)To put the flowmeter temporarily on the floor,
place it carefully with something, such as
stopper, to support it so that GF630/LF600,
LF610, LF620 and GF632 will not topple over.
* The lifting work should be executed by those qualified for crane work or slinging work
The wire or cloth
belt is used.
(a) Meter size 200mm to 900mm
Hanging hooks are provided
Figure 4.6 Transportation of GF630 series flowmeter detector
The cloth belt only can be used.
Because the wire add tha damage
to detector and covnerter body.
90°or less
Hanging hook
− 23 −
flowmeter
flowmeter
Stopper, etc. to prevent from toppling over it.
(b) Meter size 15mm to 150mm
Hanging hooks are not provided
6F8A0882
A bar, etc. to lift
the flowmeter.