Scheduling a UPS Self-Test
Select Battery Self-Test Schedule from the UPS menu to open the UPS Test Manager window
(see Figure 74). You can schedule a UPS self-test for one time only or on a monthly basis.
Figure 74. UPS Test Manager Window
The UPS Test Manager window displays a calendar at the top and the task list at the bottom. All of the
UPS self-test and UPS on/off tasks are shown in the task list. The calendar displays a red dot for the UPS
power off action, a green dot for the UPS power on action, and a blue dot for the UPS self-test action.
73
Configuring the Software