After climbing up to the tower, installation engineer A secures the fixed pulley to the
tower platform support and leads the lifting sling through the fixed pulley.
Installation engineer B secures three cable ties to the power cable connector, and then
secures the power cable to the lifting sling, as shown in
NOTE
The connector on the power cable in the figure is only an example. The actual connector may vary
according to the situation.
Figure 7-10 Binding cable ties
Installation engineer B wraps the power cable connector with a layer of PVC insulation
tape, as shown in
Figure
NOTE
Wrap the PVC insulation tape from 30 mm (1.18 in.) away from one end of the connector until it
reaches the other end of the connector. The total length of the wrapped connector is 100 mm (3.94
in.).
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Hoisting an RRU and Related Cables onto a Tower
7-11.
Figure
7-10.
46

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dbs3900Rru32682g6

Table of Contents