Installation; Unpack And Inspect - GE C70 Instruction Manual

Capacitor bank protection and control system
Hide thumbs Also See for C70:
Table of Contents

Advertisement

C70 Capacitor Bank Protection and Control System
Chapter 3: Installation

Installation

This chapter outlines installation of hardware and software. You unpack, check, mount, wire the unit, turn on power, then
install the software and configure settings.

3.1 Unpack and inspect

Use this procedure to unpack and inspect the unit.
1.
Open the relay package and check that the following items have been delivered:
C70
Mounting screws
GE EnerVista™ DVD (software and documentation)
C70 Instruction Manual (soft copy on DVD; printed copy if ordered)
UR Family Communications Guide (soft copy on DVD; printed copy if Instruction Manual ordered)
Certificate of Calibration
Test Report
EC Declaration of Conformity
Front panel label package
2.
Inspect the unit for physical damage.
3.
View the rear nameplate and verify that the correct model has been delivered. The model number is at the top right.
4.
Any protective plastic film on the front panel is normally peeled off, but also can be left on.
5.
For any issues, contact GE as outlined in the For Further Assistance section in chapter 1.
6.
Check that you have the latest copy of the C70 Instruction Manual and the UR Family Communications Guide, for the
applicable firmware version, at
C70 CAPACITOR BANK PROTECTION AND CONTROL SYSTEM – INSTRUCTION MANUAL
http://www.gegridsolutions.com/multilin/manuals/index.htm
3-1

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents