Step
Check item
4.7
Cable connectors and fibre optic cables are intact and according to instructions. Check the
termination of cables (e.g. AMP connectors), the crimping of cable lugs and ferrules. Check that
the connectors are suitable for the cables and the correct crimping tool has been used.
Check that
• insulation of the cable is not underneath the connector.
• all strands of the cable are inside the connector.
• the connector is not broken.
• the cable is deep enough in its connector.
4.8
Connection of cables to devices and terminal blocks. Check that
• the cables are connected to terminals tight enough by pulling the cable.
• the cable termination on terminals chaining is done correctly.
• bare conductors are not too far outside the terminal causing an insufficient clearance or loss of
shielding against contact.
4.9
Cables are not lying against sharp edges or bare live parts. Bending radius of fibre optic cables
³ 3.5 cm (1.38 in.).
4.10
The type, markings, insulation plates and cross connections of terminal blocks are correct.
5.
Clearances and creepage distances
5.1
Clearances outside the modules are at least 12.7 mm (0.5 in.).
5.2
Creepage distances outside the modules are at least 12.7 mm (0.5 in.).

Groundings and protection

Checks for groundings and protections are listed below. Tips for installations where
EMC emissions must be minimised are given in column Extra requirements for EMC.
Step
Check item
6
Groundings and protection
6.1
The grounding colours, cross-section and grounding points
of modules and other equipment match the circuit diagrams.
6.2
Connections of PE cables and busbars are tight enough. Pull
the cable to test that it does not loosen.
6.3
Doors equipped with electrical equipment are grounded.
6.4
Fans that can be touched are shrouded.
6.5
Live parts inside the doors are protected against direct
contact to at least IP 2x (if required).
Extra requirements for EMC
No long routes for pigtails
No long routes for pigtails
No long grounding routes. From EMC standpoint
best result is achieved with a flat copper braid.