6 HANDLING
6 - 12
Cable production method
• Peel the sheath (with the length shown below) at both ends of the cable,
and expose the shield braided wire for grounding.
• The cable must be 15m or shorter.
GOT side
(ZCAT3035-1330)
130
(5.12)
Within 230
40
(9.06)
(1.57)
2) For RS-422 cable (AC30/100/300R4-25P)
Refer to (2) (b) 1)
3) For RS-422 cable (User created cable)
Refer to the GOT-A900 series User's Manual (GT Works Version5/GT
Designer Version5 compatible Connection System Manual) for
information about the cable creation method.
• Wind cable shield material around the cable, and pull out the
grounding braided wire of the cable shield material with the length
shown below.
• Pass the grounding braided wire on the programmable logic controller
side through the core.
GOT side
(ZCAT3035-1330)
Cable shield material
130
Grounding braided
(5.12)
wire(50mm(1.97inch))
Within 150
(5.90)
Grounding braided wire(200mm(7.87inch))
Ferrite Core
Computer link module side side
40
Within 400
(15.75)
(1.57)
Ferrite Core
Computer link module side
Within 150
(5.90)
MELSEC-GOT
130
(5.12)
Unit : mm (inch)
130
(5.12)
Unit : mm (inch)